The Australian Mining Review

ALL HANDS ON DECK

- Cameron Drumond

The Carmichael coal, rail and port project will purportedl­y make up just one third of Adani’s total investment into Australia by 2022, with the Indian mining giant earmarking 1500MW worth of renewables projects and a 1 million tonnes per year agribusine­ss export mechanism.

CONSTRUCTI­ON works have started this month on Adani’s mammoth $16.5 billion Carmichael coal mine, rail and port project, two months after company chairman Gautam Adani gave the operation the green light.

The massive undertakin­g has come under intense scrutiny by environmen­talists, as well as the State and Federal politician­s since it was brought to the table six years ago.

However, Adani persevered through a myriad of red tape and court appeals, confirming in late August it would commence major constructi­on works in October.

Once developed, the Carmichael mine will be able to extract more than 2.3 billion tonnes (t) of coal over a 60 year mine life, equivalent in size to the United States’ largest coal mine – Peabody Energy’s North Antelope Rochelle in Wyoming.

Carmichael has approvals to extract 60 million tonnes per annum (mtpa) of coal each year, however phase one – to be completed by 2020 – will have an initial production rate of 25mtpa.

$3.5bn has been invested into the project to date, including the purchase of the bulk handling facility at the port of Abbot Point.

A further $3.5bn will be invested by 2020, with another $8.5bn over the next 10 years.

The combined mine, rail and port operations are expected to provide 10,000 direct and indirect jobs, as well as unlock the developmen­t potential of other proposed mines in the coal-rich Galilee Basin.

Project updates

On 6 July, Adani gave the green light for the developmen­t of the Carmichael project.

“This is the largest single investment by an Indian corporatio­n in Australia, and I believe others will follow with investment­s and trade deals,” Mr Adani said.

“We have been challenged by activists in the courts, in inner city streets, and even outside banks that have not even been approached to finance the project.

“We are still facing activists. But we are committed to this project.

“We are committed to regional Queensland and we are committed to addressing energy poverty in India.”

One of those activists was Adrian Burragubba who led a splinter group of the Wangan and Jagalingou people – one of the traditiona­l owners of lands to be accessed by the Carmichael project – asking for a judicial review of the granting of the project’s mining lease.

However, on 22 August the Queensland Court of Appeal upheld the State Government’s approval of the mining lease and awarded costs against Mr Burragubba.

An Adani spokespers­on said the company welcomed the decision as it “represente­d yet another independen­t judicial decision upholding nearly eight years of developmen­t planning and rigorous approvals, and dismisses activist claims to the contrary”.

“Mr Burragubba suggests he is acting on behalf of the Wangan and Jagalingou (W&J) community, but the W&J people voted by 294–1 to support an Indigenous Land Use Agreement with Adani,” the spokespers­on said.

“It is also another legal rebuff to activists’ use of the courts to seek to delay a project that will create 10,000 direct and indirect jobs, including a minimum 7 per cent of jobs going to traditiona­l land owners covering the almost 400km long strip from Abbot Point to central western Queensland.

“The most likely people to be harmed now by further law fare by Mr Burragubba is not the project which has considerab­le momentum, but the right of the majority group to realise a benefit.”

Other traditiona­l owners had given their support to the project.

Six days after courts upheld the approval of the mining lease, Mr Adani confirmed an October start for constructi­on, with first coal to be produced by the facility in March 2020.

Adani Australia head Jeyakumar Janakaraj said Charters Towers-based civil contractin­g firm GA Services would be among the first regional contractor­s to benefit from the start of works.

“Adani Australia’s regional content initiative­s will have long-term benefits for Queensland, particular­ly for contractor­s like GA Services who help us meet our Indigenous content targets,” Mr Janakaraj said.

Adani said it was committed to providing more job opportunit­ies for regional QLD.

“Actions speak louder than words; we have opened our regional headquarte­rs in Townsville – the first major mining operation in Australia with a regional headquarte­rs instead of basing our project in a capital city,” Adani spokespers­on Ron Watson said.

“We also have an online registrati­on for people looking to work, with more than 9000 people registered and companies advertisin­g their services through our online work portal.

“We are not just advertisin­g jobs for our project, but are scanning other job opportunit­ies that arise from the region and putting them on our website free of charge.”

“We are also proposing to have a port and rail operations centre and rail maintenanc­e yard at Bowen up and running within the next few months.”

Mr Watson said Adani would also soon announce where to base its fly-in fly-out hub for the project.

“We are very close to a decision on our FIFO hub as we gear up to get workers to and from Carmichael’s project areas,” he said.

“This is a major project in terms of size and value, and we are all hands on deck moving the project forward, with broad smiles all around.”

Funding

A report by energy analyst Tim Buckley from anti-coal research group the Institute for Energy Economics and Financial Analysis (IEEFA) said there was still doubt over whether the mine was even viable.

“All of my financial analysis over the last four years says the mine is neither financiall­y viable nor strategica­lly required or justified,” Mr Buckley said.

“Financial closure is going to be a major obstacle, I have absolutely no doubt.”

Mr Watson said he didn’t understand people who were quoted saying the project was not financiall­y viable.

“When we received the FID from the board in June, not only did that give us the ‘green light’, it also injected $400m into our coffers through equity funding to start the project with,” Mr Watson said.

“We are close to our financial close for the project and are expecting to realise a complete funding package by March next year.”

Part of that financial close would likely come via the Federal Government’s Northern Australia Investment Fund (NAIF) – a $5bn scheme to encourage and finance private sector investment in economic infrastruc­ture that benefits Northern Australia to which Adani had applied.

Earlier this year, the QLD Government said it would not stand in the way of Adani receiving funding from the NAIF.

“We will not stand in the way of those arrangemen­ts [and] in the case of the Carmichael mine, any funds will pass directly from the Federal Government to Adani,” QLD Treasurer Curtis Pitt said.

Mr Watson said once Adani had received commercial investment commitment­s it would have a better idea of how much it would require from the NAIF.

“The funding gap will be realised once we finalise funding from the internatio­nal market – at this stage a figure for funding from the NAIF has not yet been determined,” Mr Watson said.

“Numbers being thrown around in the media such as $900m, or $1bn, simply aren’t accurate at this stage.”

“Adani Australia’s regional content initiative­s will have long-term benefits for Queensland.”

Other Australian projects

The central western QLD coal mining town of Moranbah will soon boast a $100m, 65MW solar energy plant, marking Adani’s first foray into the Australian renewables sector under subsidiary Adani Renewables.

The Rugby Run solar farm will be built on a 600 hectare block that was part of the Rugby Run grazing property – and is expected to use the latest mono-PERC technology and single axis tracking systems developed to improve efficiency and output.

Further stages are planned to take the generation capacity up to 170MW.

The Rugby Run Solar Farm is expected to be completed over a 12 month period with a workforce likely to peak at up to 150 employees during constructi­on.

Upon receiving developmen­t approval from the Isaac Regional Council on 12 September, Adani Renewables chief executive Jennifer Purdie said work would start on the first stage of the solar plant by the end of the year.

“This is an exciting project in terms of its size, location, and the technology we are using,” Dr Purdie said.

“This will be Adani Renewables’ first project – the first of many – and we thank the Isaac Regional Council, in particular Mayor Anne Baker and her officers for their assistance and encouragem­ent.”

Isaac Regional Council mayor Anne Baker said the council supported responsibl­e industry developmen­t which genuinely engages with all stakeholde­rs.

“We are excited to welcome Rugby Run Solar Farm as the first renewable energy project in the region,” Mayor Baker said.

“This project continues to diversify our local economy, and will contribute towards a sustainabl­e future for both Isaac and the state.

“We look forward to the employment opportunit­ies and long-term benefits that Rugby Run will deliver to our communitie­s.”

Adani said prep work, including heritage surveys and engineerin­g design had commenced and orders for critical equipment were under way.

It also executed the initial stage of works to expedite a network connection applicatio­n with Powerlink to feed into their existing network supplying the State.

Adani said it was the first of a number of solar projects to be developed in Australia and had earmarked a total capacity of 1500MW within the next five years.

“The objective is to be the largest solar power generator in Australia by 2022,” Mr Watson said.

“Solar plays a big part for Adani as we are already the largest provider in India, which includes the world’s largest single site solar generation plant at Tamil Nadu in southern India which has a capacity of 648MW.”

The company has constructe­d 793MW of solar plant in India to date, with a further 1225MW in the constructi­on or late developmen­t phase.

Mr Watson said Adani’s strategy within the next five years would see the company’s $16.5bn investment in the Carmichael project represent just one-third of the company’s operations in Australia.

“The rest will be divided between renewables – particular­ly solar – and agribusine­ss which will represent the export of about 1 million tonnes of pulse crops each year.”

“We are currently in discussion­s with a number of agricultur­al areas – particular­ly in QLD’s Central Highlands and Darling Downs regions.”

 ?? Image: Adani Australia. ??
Image: Adani Australia.
 ??  ??
 ??  ?? Adani Australia’s head Jeyakumar Janakaraj.
Adani Australia’s head Jeyakumar Janakaraj.

Newspapers in English

Newspapers from Australia