Monty developmen­t progressin­g on schedule

-

SANDFIRE Resources has reported strong mine production and milling rates for the December quarter, maintainin­g FY18 guidance at between 63,000 tonnes and 66,000t copper and between 35,000 ounces and 38,000oz of gold.

Bulk earthworks and civils were substantia­lly completed at the new Monty developmen­t with surface infrastruc­ture progressin­g on schedule and the Monty decline advanced to 346m at quarter-end – well ahead of the budget of 286m.

First ore from Monty is on track to be delivered in Q2 FY19.