The Cairns Post

GIANT WIND FARM CONSTRUCTI­ON CRANKS UP EARLY MILESTONE

Foundation readied for mighty towers

- DANIEL BATEMAN daniel.bateman@news.com.au

CONSTRUCTI­ON of Queensland’s largest wind farm is powering ahead with the first giant turbine foundation put in place at Mt Emerald on the Atherton Tableland.

Ratch Australia has installed an 800-tonne foundation in the hilly area for its $380 million project near Walkamin.

Each foundation consists of a 50-tonne reinforced steel cage filled with about 750 tonnes of concrete.

The project, which is to be completed in September next year, will include 53 wind turbines, with blade lengths of 57m, generating up to 180.5 megawatts of power from the site.

The company says this will supply, on average, a third of the power needs of the Far North.

Walkamin residents have opposed the project from day one, claiming it will impact local lifestyle and the environmen­t.

Ratch Australia’s Anthony Yeates said the first foundation was always a special milestone in wind farm constructi­on.

“Up until this point, the focal point for constructi­on has been civil works, establishi­ng the site office and constructi­ng access roads following meticulous flora, fauna and unexploded ordnance surveys,” he said.

“Getting the first foundation poured is the first bigticket items on our scope of works that has to do directly with the wind turbines. So for us it’s a special moment that salutes years of hard work by many people in our team.”

Wind turbine components will be delivered over an eightmonth period, starting in October.

The delivery route will involve the trucks heading south from Cairns along the Palmerston and Kennedy Highways before Hansen and Springmoun­t roads are used to get to site.

“It’s exciting to see the project really begin to take shape,” Mr Yeates said. “Now that we have the foundation­s under way, we hope to have the first tower sections going up within the next two months, followed by the installati­on of the nacelles (component housings) and then the turbine blades.”.

 ?? Pictures: JUSTIN BRIERTY ?? ON TRACK: Paul McDonald, site representa­tive for Mt Emerald Wind Farm, checks over constructi­on work for the first turbines being built at Mt Emerald, near Walkamin, where the concrete pour is imminent.
Pictures: JUSTIN BRIERTY ON TRACK: Paul McDonald, site representa­tive for Mt Emerald Wind Farm, checks over constructi­on work for the first turbines being built at Mt Emerald, near Walkamin, where the concrete pour is imminent.
 ??  ?? READY: Project developmen­t manager Neil Weston at the base of the first tower.
READY: Project developmen­t manager Neil Weston at the base of the first tower.

Newspapers in English

Newspapers from Australia