The Chronicle

Wagners lashes council

- MATTHEW NEWTON

WAGNER Corporatio­n director Denis Wagner has lashed out at Toowoomba Regional Council in the wake of a court judgement worth millions.

The Court of Appeal delivered a mixed bag for Wagners and Toowoomba Regional Council on Tuesday afternoon in a long-running legal dispute over tens of millions of dollars of infrastruc­ture charges.

The saga, which had dragged on for more than three years, saw the Court of Appeal agree with a May 2019 decision by the Planning and Environmen­t Court which cleared Wagners of having to pay more than $20 million in stormwater infrastruc­ture charges across the whole Wellcamp developmen­t.

The court found the decision to levy stormwater charges on infrastruc­ture that caused no additional demand on the stormwater system was unlawful.

But in a win for the council, the court ruled that Wagners’ original, successful appeals against the traffic trunk infrastruc­ture charges were dismissed, allowing the council to charge as per the infrastruc­ture charges notice.

Mr Wagner said the company was reviewing the court decision and what action to take.

“One of the biggest frustratio­ns with the Toowoomba Regional Council is their lack of willingnes­s to help drive new industry in this region,” he said.

“There has been a significan­t cost to both us and the ratepayers to run this action and what the council has achieved is a much worse result for the people it represents.

“We have asked for many years that the charging regime that is applied to the Wellcamp Business Park be consistent with charges applied to other industrial developmen­ts within the Charlton Wellcamp area.

“After analysis of charges applied to competing developmen­ts, it is apparent the council does not apply the rules consistent­ly for all developers.”

Mr Wagner said the Court of Appeal decision to uphold the previous ruling on stormwater infrastruc­ture was really one of common sense.

He said that for traffic infrastruc­ture charges: “We have never suggested we should not pay the appropriat­e amount however, we do have concerns that the Council can pick an arbitrary figure and does not have to apply a charge that reflects the true cost of the infrastruc­ture.”

matthew.newton@thechronic­le.com.au

 ??  ??