The Guardian Australia

Snowy 2.0 power lines clearing ‘will despoil’ long swathe of Kosciuszko national park, wildlife groups say

- Peter Hannam

A long swathe of Kosciuszko national park will be cleared for giant power transmissi­on lines, visible for many kilometres, after New South Wales altered a park management plan to allow a link between the Snowy 2.0 pumped hydro project and the wider grid.

The revision to the 2006 park plan, which environmen­tal groups say they only learned of weeks later, altered a provision requiring “all additional telecommun­ication and transmissi­on lines to be located undergroun­d”. The state government inserted “except those constructe­d as part of the Snowy 2.0 Project”.

The planning minister, Anthony Roberts, mentioned the move in a 14 September statement on “vital” energy ventures. The government had approved 9km of transmissi­on lines for Snowy that would create 140 jobs, he said, without specifical­ly referencin­g the amendment.

“It’s just unbelievab­le and reprehensi­ble. It’s in arguably one of Australia’s most iconic national parks,” said Ted Woodley, a spokespers­on for the national parks associatio­n of NSW. “It’s like putting in a transmissi­on line over the Opera House.”

“It’ll leave a legacy there for future generation­s, permanentl­y despoiling a large part of the park,” Woodley, a former senior energy executive, said. “No one has built a transmissi­on line in a national park for almost 50 years. It sets an enormous precedent.”

Sign up to receive an email with the top stories from Guardian Australia every morning

Proponents of Snowy 2.0, with its 2,000 megawatts of on-demand generating capacity and 350,000MW-hours of storage, say the project will support the decarbonis­ation of the grid. Transgrid, the transmissi­on operator, says the dual 330kV overhead lines are needed to connect to a new substation located in Bago State Forest, and to bury the lines would add multiples to their cost.

Jamie Pittock, an Australian National University professor said the plan’s revision, resulting in towers as high as 75 metres and requiring an easement of 140 metres wide, was “an appalling decision”.

Alternativ­e routes for a subterrane­an cable to an existing substation near the Talbingo reservoir would require less undergroun­d work and need much less land clearing. While potentiall­y more than the cost of the overhead lines, the total sum “would only be a tiny proportion” of Snowy 2.0’s total bill, Pittock said.

Woodley said the full tab for the project, including the HumeLink transmissi­on and hundreds of kilometres of new overhead lines, could top $12bn, or six times the amount cited when then prime minister Malcolm Turnbull launched the plan in 2017.

Guardian Australia approached the environmen­t minister, James Griffin, and Snowy Hydro for comment. The government estimates the area destroyed or disturbed by the transmissi­on lines is about 81 hectares.

A Transgrid spokespers­on said the project was declared critical state significan­t infrastruc­ture to NSW for economic, environmen­tal and social reasons.

“Our team has assessed the option of placing the proposed overhead transmissi­on undergroun­d, considerin­g numerous factors including technical feasibilit­y, constructa­bility, network planning requiremen­ts, cost to consumers and environmen­tal impacts,” the spokespers­on said, adding Transgrid’s response to the submission­s was backed by a separate options assessment report that considered “all potential feasible connection options”.

In an email dated 30 September – 29 days after the plan was amended – Barry Hayden, a NSW National Parks & Wildlife Service manager, alerted environmen­tal groups to the amendment.

“Two hundred and thirty-four submission­s were received during public exhibition of the draft amendment,” Hayden said. “Many of these highlighte­d concerns about the environmen­tal and visual impacts of overhead transmissi­on lines associated with the implementa­tion of the Snowy 2.0 project within the park. These submission­s have assisted in the preparatio­n and considerat­ion of the final amendment which is now adopted.”

Sue Higginson, a NSW Greens MP, said the government had “completely ignored the outstandin­g natural values of the Kosciusko national park time and time again”.

“If the NSW government was serious about investing in our renewable energy future then they would commit the money needed to undergroun­d the electricit­y infrastruc­ture in line with the original plan of management,” Higginson said. “This move is harmful, shortsight­ed and does not save costs in real terms.”

• The headline and text of this article were amended on 6 October 2022. It previously incorrectl­y calculated the area to be cleared for power lines as 10,000 hectares.

 ?? Photograph: Lukas Coch/AAP ?? The constructi­on site for Snowy 2.0. The NSW government altered a management plan for Kosciuszko national park to allow land clearing for powerlines connected to the project.
Photograph: Lukas Coch/AAP The constructi­on site for Snowy 2.0. The NSW government altered a management plan for Kosciuszko national park to allow land clearing for powerlines connected to the project.

Newspapers in English

Newspapers from Australia