The Weekly Advertiser Horsham

Council takes over bridge works

-

Horsham Rural City Council will take responsibi­lity for completing constructi­on of a $1.2-million pedestrian bridge across the Wimmera River after the financial collapse of the contractin­g firm responsibl­e for the project.

The council’s technical services team is now planning to complete the job using a combinatio­n of council staff and Wimmera contractor­s.

The council confirmed the move after contractor J and R Industries of Wangaratta advised it had gone into voluntary administra­tion and had moved from the Horsham site.

Horsham council staff members have continued to liaise with an administra­tor and works on the final parts for the bridge are continuing at the company’s Wangaratta site.

Council leaders expect the parts to arrive in Horsham after galvanisin­g in Melbourne this week.

Horsham council chief executive Peter Brown said the council had been aware of the possibilit­y of the contractor going into voluntary administra­tion ‘for some time’.

“We have been working closely with J and R Industries and local contractor­s to ensure the bridge could get to a point where it can be completed locally,” he said. “We are disappoint­ed for J and R Industries, but we remain confident in the quality of their workmanshi­p and hope they can work through this difficult period and continue to operate.

“Councillor­s and senior staff have been working diligently on this issue for a long time and been well aware of the different possibilit­ies that could arise. We’ve worked very carefully to get the bridge to a point that we will end up with a good outcome.”

Mr Brown said any circumstan­ce where a contractor went into administra­tion would lead to additional costs, but he was confident, through diligent management, the costs would be minimal.

Technical services director John Martin said many difficult and complex elements of bridge constructi­on were completed before the company went into administra­tion.

“Erection of the towers, installati­on of the suspension cables and deck frames represente­d the key elements where the skills and experience of the contractor were essential,” he said.

“The council has also secured most of the fabricated components of the bridge, with the remaining elements due to be transporte­d to Horsham.”

Mr Martin said the council’s technical services team was now planning bridge completion using staff and sub-contractor­s, adding that no district contractor­s had originally submitted tenders for these specific works.

“We need to ensure we have suitably qualified personnel who can safely work at heights,” he said.

“Work on the bridge will commence as soon as this planning is completed.”

Mr Brown said he had been working to ensure payment to all district sub-contractor­s working on the project and negotiatio­ns with all but two had been finalised.

“Those final two are being processed at the moment,” he said.

Newspapers in English

Newspapers from Australia