Townsville Bulletin

Station left powerless

Delays keep new energy plant off grid

- TONY RAGGATT tony.raggatt@news.com.au

ONE of the world’s most advanced renewable energy plants is sitting idle, unable to generate electricit­y about six months after it was completed in North Queensland.

The $160 million hybrid wind, solar and battery storage power station was developed outside Hughenden west of Townsville, promising to power 35,000 homes.

But “weak” transmissi­on line infrastruc­ture connecting the site to the electricit­y grid, the North Queensland floods earlier this year and concern about the plant’s safe integratio­n into the network are behind delays in its connection.

In a market update, developer Windlab said the Kennedy Energy Park had been completed “for a number of months” but was experienci­ng delays in generator performanc­e standards and registrati­on as a generator.

“This is delaying energisati­on and commission­ing,” the company said.

“Negotiatio­ns are progressin­g with the grid operator and the project’s (engineerin­g, procuremen­t and constructi­on) contractor to resolve the situation as quickly as possible.”

Windlab chief financial and operating officer Rob Fisher said he looked forward to seeing the power station energised “this (September) quarter”.

A spokesman for the Australian Energy Market Operator said power system security was their core responsibi­lity.

“There is high interest in renewable connection­s across the National Electricit­y Market, generally in regions remote from existing generation sources, load centres and power transmissi­on infrastruc­ture. These are increasing­ly requiring detailed technical assessment­s to confirm (their) ability to safety operate without adversely impacting power system stability.

“Importantl­y, our focus is on the stability of new generation plant and the safe integratio­n of all new generation into the broader power transmissi­on system.”

Grid connection risk is increasing as more renewable energy projects are built in areas where transmissi­on lines are not “strong” enough to carry large amounts of intermitte­nt generation.

AEMO is requiring some developers to add extra equipment to strengthen the grid and can also restrict the amount of energy a project operator can send into the grid.

Windlab has been required to add equipment including a synchronou­s condenser to provide power at short notice to stabilise the grid when voltage or frequency deviates from safe levels.

Windlab has also struck delays over another North Queensland wind farm project at Lakeland. Financiers Infrared Capital Partners withdrew from that project last year, citing an inability to price risks associated with grid connection.

Windlab says lack of energy policy and co-ordination is creating technical, market and investor uncertaint­y, which flows through to an uncertain operating environmen­t.

New connection standards were introduced last year requiring higher technical performanc­e from renewable plants.

“The challengin­g regulatory environmen­t has created additional uncertaint­y around grid connection capacity in North Queensland,” Windlab said in its 2018 annual report.

 ??  ??

Newspapers in English

Newspapers from Australia