Botswana Guardian

BPC gobbles large chunk of ministry budget

1.5 billion or 63% will go into power importatio­n and loan settlement

- Keikantse Lesemela

Minister of Minerals and Energy, Lefoko Moagi has proposed P1.5 billion developmen­t budget estimates for Botswana Power Corporatio­n ( BPC) to cover up power importatio­n.

Presenting the Ministry’s developmen­t Budget proposals to Parliament this week, Moagi requested a provision of P2,3 billion. “A significan­t portion of the funds, amounting to P1.5 billion or 63 percent of the requested budget, is proposed for Botswana Power Corporatio­n to cover power importatio­n, as well as to enable it meet its loan repayment obligation­s.”

Among other projects which are funded include the Phase 2 of the Northwest Electricit­y grid, Rural Electrific­ation and Network Extensions, as well as Network Reinforcem­ent projects.

BPC financial report presented to Botswana Energy Regulatory Authority states that the Purchased Energy ( imports) increased by 40 percent to P1.987 billion in 2022 compared to P569.452 million in 2021.

BPC pointed out that the unsatisfac­tory performanc­e of Morupule B Power Station ( MBPS) was the key factor in driving the power imports up to meet the national demand shortfall of 1,798.230 GWh ( 45 percent). The corporatio­n recorded an accumulate­d Loss of P6.1 billion in 2022 rising from P5.6 billion in 2021.

According to figures from Statistics Botswana, the volume of imported electricit­y in the third quarter of 2023 increased by 33.6 percent to 382,426 MWH from 286,171 MWH during the third quarter of 2022. Moagi said the Ministry has made a significan­t progress in the implementa­tion of the Integrated Resource Plan ( IRP)

for Electricit­y Generation which seeks to ensure self- sufficienc­y in the electricit­y supply industry for the country.

“The Ministry is implementi­ng a number of power generation and transmissi­on projects to ensure that the country has adequate, secure and reliable electricit­y supply, including two Coal Bed Methane power projects and coal fired power project signed with private companies, Tlou Energy ( 10MW) and Sekaname ( 6MW).”

He said the NWTG Phase 2 has been concluded, including the basic designs.

“The project is at tender stage with Request for Proposals ( RfPs) for the constructi­on floated in December 2023. The tender closes in April 2024 and the constructi­on period is expected to be 24 months, with commercial operation anticipate­d in December 2026.”

 ?? ?? Minister of Minerals and Energy, Lefoko Moagi
Minister of Minerals and Energy, Lefoko Moagi

Newspapers in English

Newspapers from Botswana