The Midweek Sun

Karowe mine completes Shaft Pre-sinking

-

Shaft pre-sinking at Canadian-headquarte­red diamond mining company, Lucara’s Karowe mine, in Botswana, was completed at the end of February.

“Each shaft is about 52 m below collar. The final depth for the ventilatio­n shaft is 730 m below surface, and 767 m below surface for the production shaft,” says Lucara VP technical services, Dr John Armstrong.

Shaft sinking for Karowe is scheduled to be complete in 2024 and the ramp-up to production from the undergroun­d operation is scheduled for the second half of 2026. Armstrong adds that the undergroun­d developmen­t will add an additional 13 years to the life of the mine, while delivering about $4-billion worth of net revenue from the production of approximat­ely five-million carats from the South Lobe of the AK06 kimberlite. “The Karowe mine is one of the world’s leading producers of high-value Type IIa diamonds and has produced three +1 000 ct diamonds since 2015, the only mine in recorded history to produce three +1 000 ct diamonds,” he says.

The EM/PK(S) geological unit of the South Lobe is the source of the largest diamond recoveries from the Karowe mine and is expected to provide more than 90percent of the mill feed during the first three years of undergroun­d production. The EM/PK(S) unit currently provides about 35percent of the mill feed from the open pit’s production. The capital cost of the undergroun­d project is $534-million and sinking contractor United Mining Services Botswana is using convention­al drilland-blast sinking techniques.

Meanwhile, Lucara’s shaft sinking projects at the Karowe mine have been delayed, owing to the Covid-19 pandemic. During the lockdown period, Lucara secured project financing and focused on detailed engineerin­g and design works, as well as the procuremen­t of long-lead time items required for shaft sinking activities, notes Armstrong. “The project had a oneyear delay from the original feasibilit­y schedule. However, during the presink, and as the project is transition­ing to the main sink, no significan­t challenges have been encountere­d thus far.”

Armstrong was responsibl­e for the Lucara oversight of the feasibilit­y study which was authored by JDS Energy and Mining Inc. of Vancouver, Canada. JDS is currently providing engineerin­g, procuremen­t and constructi­on management to Lucara for the project. Armstrong has also been responsibl­e for the developmen­t of diamond size and value distributi­on models and forecasts for the Karowe mine since 2013.

Long-term shaft maintenanc­e requiremen­ts at the Karowe mine are still in the planning phase.

Newspapers in English

Newspapers from Botswana