MEG Energy pushes for Enbridge to scrap plan for pipeline

- NIA WILLIAMS

CALGARY Oilsands producer MEG Energy has written to the federal energy regulator to oppose pipeline company Enbridge Inc’s plan to introduce long-term fixed volume contracts on its Mainline system.

MEG’S open letter to the National Energy Board regulator, filed on Friday, makes it the largest producer so far to call for Enbridge to scrap its Mainline plan because of how it will affect producers’ ability to ship crude to market.

The 2.85 million barrel per day Mainline is North America’s largest pipeline system and a crucial conduit for Canadian producers exporting crude to the United States.

Enbridge’s plan to switch from a monthly nomination system to “contract carriage” comes as Canadian export pipelines are so constraine­d the Alberta government has imposed oil production curtailmen­ts, and has drawn fierce criticism from small producers.

“It is MEG’S position that Enbridge’s contract carriage proposal should be abandoned, as it is not in the overall public interest,” the letter signed by MEG’S CEO Derek Evans said.

Enbridge did not immediatel­y

It is MEG’S position that Enbridge’s contract carriage proposal should be abandoned.

respond to a request for comment.

The pipeline company launched a two-month open season to solicit bids for contracted space on 90 per cent of the Mainline on Aug. 2. Under the current monthly nomination system, demand to ship on the Mainline regularly exceeds capacity, forcing Enbridge to ration, or apportion, space.

MEG, which produces 90,000 bpd at its Christina Lake project in northern Alberta, is worried the changes will prevent it from meeting previous commitment­s to ship crude to the Gulf Coast on the Flanagan South pipeline, which the Mainline feeds.

Smaller producers are concerned large U.S. refiners like BP Plc will snap up most of the contracted capacity, leaving them scrambling to secure space on the smaller slice of the pipeline open for spot volumes.

ARC Energy Research Institute analyst Jackie Forrest said the 10 per cent of the Mainline left open for spot shipping would likely be heavily rationed, resulting in more barrels getting stranded in Alberta each month and being sold off cheaply.

“If you shrink spot to 300,000 bpd you are going to see that space be many many times over-allocated,” Forrest said. “As the level of apportionm­ent increases, the level of (price) discount increases.”