Cape Breton Post

Water testing time

Flushing of new main to be followed by pressure and bacteria tests

- BY JEREMY FRASER jeremy.fraser@cbpost.com Twitter: @CBPost_Jeremy

Water main upgrades at two Sydney Mines locations have been completed.

New water mains were installed at the intersecti­ons of Main Street and Pond Road as well as Main Street and Diggin Street along with the entire length of Diggin Street.

“The old mains had reached the end of their useful life, so the installati­on of this new main will strength the backbone of the water infrastruc­ture in the community for many years to come,” said Greg Campbell, Cape Breton Regional Municipali­ty water system engineer.

“Improvemen­ts to fire protection in the area are also expected to be realized with the new properly sized transmissi­on main,” said Campbell. “Residents will not notice any change to their current service, but the risk of future disruption­s associated with the aging mains have been greatly reduced.”

Water main upgrades began on Aug. 14 in Sydney Mines. Work was expected to be completed within four weeks of the start date.

The municipal water utility is continuing work at the locations with water testing tentativel­y scheduled for this week.

Testing is expected to be completed in phases. The first portion of the new water main will be tested from the Main Street-Pond Road intersecti­on to Tobin Road near Bushells Lane.

The first testing was tentativel­y set for Monday night with flushing of the new main to take place, followed by disinfecti­on, pressure testing and bacteria testing.

According to municipal officials, the process usually takes several days on average to complete.

Once testing is complete with acceptable results, the new main will be put into service and the connection of the new services will begin at the contactor’s discretion.

Jillian Moore, spokespers­on for the CBRM, said nighttime flushing in this case has the potential to cause dirty water in Sydney Mines, which is why

the work is being done at night to minimize inconvenie­nce to customers.

Meanwhile, in another constructi­on project on the Northside, the municipali­ty

confirmed the culvert replacemen­t on Regent Street in North Sydney is nearing completion.

 ?? SUBMITTED PHOTO ?? The Cape Breton Regional Municipali­ty water utility says the installati­on of water main upgrades in Sydney Mines has been completed. The process will continue with testing tentativel­y scheduled for this week. The image shows the locations of those...
SUBMITTED PHOTO The Cape Breton Regional Municipali­ty water utility says the installati­on of water main upgrades in Sydney Mines has been completed. The process will continue with testing tentativel­y scheduled for this week. The image shows the locations of those...

Newspapers in English

Newspapers from Canada