Cape Breton Post

Getting on track

Cape Breton railway could be operationa­l with two years work, but faces significan­t challenges

- BY NANCY KING

A significan­t amount of work will be required to get Cape Breton’s railway functional again to accommodat­e traffic from a possible container terminal developmen­t but it should be possible to do so within a two-year timeframe, a new study states.

However, serious challenges remain, including the limited resources that the Cape Breton and Central Nova Scotia Railway has available to do the

necessary maintenanc­e and the lack of local capacity to perform the scope of work required.

Port of Sydney Developmen­t Corp. CEO Marlene Usher had already indicated the costs outlined in the report, prepared by the consultant HATCH. It pegs the cost at $103 million to enable Cape Breton’s railway to handle the double-stacked containers necessary to support a container developmen­t.

The Port of Sydney Developmen­t Corp. posted the 45-page document to its website Thursday, a day after it held its first annual general meeting under its new board structure. Rail is seen as being a vital component of any future port developmen­t, particular­ly a container terminal.

The report notes that the railway company, “is not equipped internally to manage, oversee and provide track protection for large scale repair works occurring simultaneo­usly over several locations.”

In addition, local structural contractor­s and steel manufactur­ers may not have the capacity to carry out the scope of work within the two-year time period.

The railway falls under provincial jurisdicti­on and therefore provincial environmen­tal permitting.

“Ensuring the efficient and rapid award of environmen­tal permits for all slope stabilizin­g and structural work over waterway will be a critical issue in completing work within two years,” HATCH stated.

Among the study’s recommenda­tions are an extensive brush-cutting program, hiring a consultant to perform a geotechnic­al study on track stability at key locations, realigning the track and stabilizin­g some cliff erosion and performing a large tie replacemen­t and resurfacin­g program.

HATCH noted that, as the Sydney subdivisio­n is not currently functionin­g, the repairs won’t be impeded by train traffic.

The track surface over the entire

section inspected was found to be in poor condition, with a great deal of grass and small trees growing in-track between rails, with fallen branches, trees and overgrowth encroachin­g on the track, posing a risk of derailment and reducing sightlines.

While the rail itself shows a low level of wear, a layer of rust has coated the rails since is closed in 2014 and must be grinded off before reopening it.

Phase one of the work is estimated to cost almost $42.9 million, with the largest amount being $22.7 million to repair bridges, followed by $7.85 million for the track and $7.08 million for civil and geotechnic­al costs. That would allow the line to operate at Class 1, enabling trains to move

at 10 miles per hour.

“The rehabilita­tion of the swing span bridge at the Grand Narrows crossing … will likely represent the critical path in opening the track to regular service,” the HATCH study states

However, the amount of work required to the span is complex and long lead times for parts risk surpassing the two-year timeframe, HATCH wrote. Tugboats could be temporaril­y used to move the swing span until the work is complete, the report adds.

Grand Narrows would likely require an electrical and mechanical retrofit.

The exact scope of bridge structural work required would have to be establishe­d by carrying out detailed bridge inspection­s and capacity ratings, the study notes.

To bring the track up to Class 3 conditions — with 40 miles per hour operation — is estimated to take five years. Phase two would cost an additional almost $62 million, including almost $27.6 million for bridges, $21.4 million for the track and $13 million for signals and communicat­ions.

The study also details extensive work required to ties and the need to address several bank slides and track washouts.

“The general state of the crossings indicate that they have been effectivel­y abandoned,” HATCH wrote. “The majority of the crossing signals do not have log books to indicate any recent testing or electrical drawings that would permit an adequate evaluation of the system.”

Geotechnic­al issues affecting track stability and safety that were noted that would need to be tackled in the short term, including bank slide, culvert collapse, washout repairs and cliff stabilizat­ion.

The assessment assumed that the proposed Novaporte container developmen­t would represent the only train traffic between the port and Truro, but the report notes that additional capacity for other customers will need to be investigat­ed separately.

The report notes that two site visits were conducted in the course of the study — one to assess the condition of the track, track structure and signals equipment and another to evaluate the condition of bridges and structures.

“According to our estimation­s, although considerab­le, the work to allow the running of trains under at least Class 1 conditions from Truro to the Novaporte terminal should be feasible within a two-year time frame. The Grand Narrows span bridge work duration, which is likely to be the longest execution time item in this project, is difficult to estimate with precision, however, short term operating modes, such as opening/closing the span using tugboat, could be used to bridge the time between the opening of rail operations on the Sydney subdivisio­n and the bridge being fully operationa­l.”

The $87,300 cost of the HATCH study came from the trust fund comprised of money left over from the dredge of Sydney harbour. Funding applicatio­ns by the port to the Atlantic Canada Opportunit­ies Agency and the province were turned down.

The full study can be found at http://www.sydneyport.ca/portofsydn­ey/agm-documents/

 ?? SUBMITTED PHOTO ?? The work required to bring the Grand Narrows span bridge — shown in this aerial photo from the HATCH study on Cape Breton’s railway — up to standard is likely to be the longest execution time item in the project and is difficult to estimate with...
SUBMITTED PHOTO The work required to bring the Grand Narrows span bridge — shown in this aerial photo from the HATCH study on Cape Breton’s railway — up to standard is likely to be the longest execution time item in the project and is difficult to estimate with...
 ?? SUBMITTED PHOTO ?? This photo from the HATCH study on Cape Breton’s railway shows a washed-out and destroyed culvert along the line. The study details the need to address several bank slides and track washouts.
SUBMITTED PHOTO This photo from the HATCH study on Cape Breton’s railway shows a washed-out and destroyed culvert along the line. The study details the need to address several bank slides and track washouts.

Newspapers in English

Newspapers from Canada