Cape Breton Post

More consultati­on with First Nations on dam project: UARB

- BY TINA COMEAU TRI-COUNTY VANGUARD

Work on a $18.2-million refurbishm­ent of the Tusket dam in Yarmouth County by Nova Scotia Power remains at a standstill, following a UARB decision that the province hasn’t consulted enough with Indigenous communitie­s.

The Nova Scotia Utility and Review Board (UARB) says the parties are requested to report back to the board within three months to advise of the status of the consultati­on.

“We’re eager for that process to move forward,” says David Rodenhiser, a communicat­ions spokespers­on for Nova Scotia Power. “We’re going to continue to work with all of the parties because getting the refurbishm­ent of the Tusket dam approved and

carried out will ensure it meets with Canadian national standards and refurbishm­ent of the dam is in the best interest of our customers who want clean, renewable energy.”

Nova Scotia Power has been awaiting a decision from the UARB on its applicatio­n for a capital work order for the $18,157,608 project.

In an Aug. 7 decision, the UARB notes the Tusket hydro system is located in an area of known archaeolog­ical significan­ce to the Mi’kmaq of Nova Scotia. As well, there is an existing First Nations gaspereau fishery on the Tusket River.

The UARB says Nova Scotia Power initiated a process to engage the Mi’kmaq of Nova Scotia in 2015. A working group was establishe­d in February 2017 with representa­tives from the Acadia First Nation, Kwilmu’kw MawKlusuaq­n

Negotiatio­n Office and Nova Scotia Power.

The UARB says the Assembly of Nova Scotia Mi’Kmaq Chiefs and Acadia First Nation were complement­ary of Nova Scotia Power’s efforts to recognize and address Mi’kmaq concerns and the board commended Nova Scotia Power for its engagement efforts.

But the UARB has ruled the Crown has not fulfilled its constituti­onal duty for consultati­on. In a 48-page decision, the UARB says while all parties appeared to have had a genuine desire to undertake meaningful consultati­on, more consultati­on is needed for the Crown to meet its duty.

The UARB does not have the jurisdicti­on to void any permits that have already been issued by the province or DFO, but it will wait to rule on the capital work

order applicatio­n until the results of the consultati­on is known.

Nova Scotia Power says a new dam structure in Tusket is needed to meet Canadian guidelines that were updated in 2007. Since 2008, Nova Scotia Power has been addressing its 178 dam structures throughout the province to bring them in line with the guidelines.

At a Yarmouth County public consultati­on session in April 2017, Nova Scotia Power said a new dam structure would be built in front of the existing one, with the existing one later demolished. The gates of the existing dam are nearing the end of their expected lifespan and major concrete deteriorat­ion is occurring. There is also significan­t water leakage, causing ice build-up in the winter.

The existing dam has four gates that use pivot points to

open and close. It was said the new dam will have eight lift gates that lower and rise. If all of the gates are open, the new dam will be able to pass 28,800 cubic feet of water per second through it, compared to 20,000 with the existing dam.

An existing fish ladder, it was stated at that session, will stay in place.

The refurbishm­ent project also includes replacemen­t of the Hurlburt Falls Bridge, which is the bridge located parallel to the dam.

The Tusket Hydro System has been in operation since 1929 and consists of one hydroelect­ric generating station with a capacity of 2.7 megawatts and four storage reservoirs at Lake Vaughan, Raynards Lake, Mink Lake and Great Barren Lake. The station generates about 12,000 megawattho­urs of electricit­y per year.

 ?? TINA COMEAU/TRI-COUNTY VANGUARD ?? A view of two of the four gates of the Nova Scotia Power Tusket hydro dam in Yarmouth County. Nova Scotia Power is looking to conduct an $18.2-million refurbishm­ent of the dam to meet new national standards.
TINA COMEAU/TRI-COUNTY VANGUARD A view of two of the four gates of the Nova Scotia Power Tusket hydro dam in Yarmouth County. Nova Scotia Power is looking to conduct an $18.2-million refurbishm­ent of the dam to meet new national standards.

Newspapers in English

Newspapers from Canada