Cape Breton Post

‘OPTIMISM BIAS’ BLAMED FOR MUSKRAT FALLS OVERRUNS

Hydroelect­ric projects particular­ly risky, says economics professor

-

Hydroelect­ric dams are particular­ly vulnerable to cost and schedule overruns, an expert testified Monday at the start of a public inquiry into the Muskrat Falls hydro megaprojec­t in Labrador.

Oxford University economics professor Bent Flyvbjerg, who is described on his faculty page as “the most cited scholar in the world in megaprojec­t planning and management,” took the stand in Happy Valley-Goose Bay, N.L., to outline common mistakes and causes of cost overruns of such projects.

He said hydroelect­ric projects are particular­ly risky, seeing average cost overruns of 96 per cent and schedule overruns of 32 per cent, with little change over time since the 1950s.

The report also noted that dams doubled their budgets on average.

“The context is that building a hydroelect­ric dam is very risky,” Flyvbjerg said.

“It seems to be a very persistent phenomenon that has been with us for decades.”

The massive Labrador dam and powerhouse harnessing the lower Churchill River near Happy Valley-Goose Bay still isn’t complete, but its price tag has climbed to $12.7 billion with the bill going to a province of just 530,000 people.

The independen­t inquiry, led by provincial Supreme Court Justice Richard LeBlanc, will examine how the project was approved and executed, and why it was exempt from oversight from the Public Utilities Board.

Flyvbjerg, who has also consulted on megaprojec­ts in several European and Asian countries, was commission­ed by the inquiry to compile a report giving global context and best practices for success in megaprojec­ts, but not specifical­ly looking at the case of Muskrat Falls.

The report, co-authored by Alexander Budzier, surveyed 274 megaprojec­ts around the world, including over 40 in Canada. Flyvbjerg defines a megaprojec­t as one that costs more than $1 billion.

Data from the report shows that hydroelect­ric dams are “riskier than all other projects, except nuclear.”

Flyvbjerg said many projects are affected by underestim­ated costs and schedule, overestima­ted benefits, and lack of independen­t oversight.

The report cited optimism bias and political bias as the root causes of high cost overruns _ optimism bias being unintentio­nal misunderst­anding of costs and schedule, and political bias being intentiona­l deception.

“The real cause of the cost overruns and schedule overruns is that planners were optimistic about all these things,” said Flyvbjerg.

Political bias, also known as “strategic misreprese­ntation,” explains when project managers intentiona­lly “overestima­te benefits and underestim­ate cost and schedule” to ensure their projects get a green light.

Optimism bias is a psychologi­cal term describing the “systematic tendency for people to be overly optimistic about the outcome of planned actions, includes underestim­ating the likelihood of negative effect.”

The report recommends outside, independen­t oversight in the early stages to “de-bias” projects. Flyvbjerg said too many project managers take an “inside view” of projects which creates conditions for bias taking over.

Other recommenda­tions include as much transparen­cy of project developmen­t as possible, and assessing groups of similar projects to adjust estimates early on, as well as bringing in experience­d advisers.

The summary of the report includes a note that “the maturity of leadership in capital investment projects is often perceived to be lacking.”

When questioned by cocounsel Barry Learmonth, Flyvbjerg said projects are generally more successful when stakeholde­rs, like Indigenous groups and environmen­tal groups, are engaged in the process early on.

“We’ve generally found that it does make sense to involve all stakeholde­rs as early as possible,” said Flyvbjerg.

“It’s like with the biases, if you don’t do it, it’s going to come back to haunt you ... it’s much more expensive to take these things into account if you have to do it later on in the process.”

Flyvbjerg is the first of many witnesses to testify before the inquiry, the first phase of which is focused on the project’s sanctionin­g and the involvemen­t of the Public Utilities Board.

The hearings will conclude in August 2019, with a final report expected by Dec. 31., just after the next provincial election.

LeBlanc opened the day with some brief comments on the scope of the inquiry, noting that some evidence will not be made public based on ongoing court cases, like one regarding water management on the Churchill River that is currently before a Quebec court.

Newspapers in English

Newspapers from Canada