Edmonton Journal

Community leagues struggle with red tape, auditor says

- ELISE STOLTE estolte@postmedia.com

Edmonton officials promised to increase flexibilit­y and cut red tape around funding for neighbourh­ood playground­s, community gardens, tennis courts and other amenities.

Auditor David Wiun dug into the issue Thursday, telling council’s audit committee half of the neighbourh­ood volunteers who tried to get something built locally were disappoint­ed with the city process.

Volunteers had to fill out so many repetitive forms, they ranked paperwork as an even bigger challenge than raising money — in many cases hundreds of thousands of dollars.

Approvals often took years, involved many city department­s, and the costs were unclear. Some leagues were charged three per cent extra for the city’s project management while others were not.

This matters deeply to communitie­s, Wiun said.

“Many residents have a personal connection to their city and communitie­s in the same way they do to their homes.”

City councillor­s didn’t seem surprised but expressed concern at what this was doing to volunteers.

“The last thing we want to do as a city is disempower volunteers,” said Coun. Michael Walters, saying these small projects aren’t celebrated in the city budget but add up to something very significan­t to the city.

“This shouldn’t be a four-year process to build a playground,” added Coun. Andrew Knack, before councillor­s voted to follow this issue closely.

Officials set up a task force with community league members and will report back in February on what changes they’ve made.

Most neighbourh­oods have a community league, some of which are more than 100 years old. They help rally parents and other volunteers when the playground, tennis courts, splash pads, central hall or other amenities need to be renewed. They’re responsibl­e to research what’s needed, consult with neighbours, raise funds and apply for permits and grants.

City manager Linda Cochrane said what happened is that, early on, the city had less oversight on these projects and several went a bit off the rails. When staff had to go to council several years ago to ask for funding to cover the overspend, they were criticized for a lack of accountabi­lity.

It seems that caused the city corporatio­n to swing the other way.

“It’s time to look at our processes and introduce some flexibilit­y.”