Edmonton Journal

Killing off Keystone sets `a precedent'

Oil industry officials say Biden's decision could impact other infrastruc­ture work

- CHRIS VARCOE Chris Varcoe is a Calgary Herald columnist. cvarcoe@postmedia.com

On his first day as U.S. president, Joe Biden pulled the pin on Keystone XL.

The political fallout reverberat­ed on both sides of the border, as pipeline opponents set their sights on other infrastruc­ture that transports Canadian oil into the U.S., such as Enbridge's Line 3 replacemen­t project.

“It should set a precedent,” said Anthony Swift of the U.S. -based Natural Resources Defense Council (NRDC). “The same case that Keystone XL failed to pass, Line 3 certainly fails to pass, as well.”

Hours after his inaugurati­on, the 46th U.S. president revoked a necessary permit for Keystone XL, a cross-border oil pipeline that has been under constructi­on since last year — and one Biden has long promised to block over climate considerat­ions.

Calgary-based TC Energy announced Wednesday morning it was suspending the developmen­t. The decision will lead to thousands of workers losing their jobs.

It didn't say so officially, but the project will likely end up in the graveyard of unsuccessf­ul pipeline proposals, joining Energy East and Northern Gateway.

But the broader question needs to be considered: Will the decision have ramificati­ons for other pipelines required to move Canadian oil and natural gas to the country's largest customer?

“It does set a precedent because this has not been done before ... something of this scale and this kind of ping-pong approval process and challenge,” said Chris Bloomer, Canadian Energy Pipeline Associatio­n chief executive.

“It is a risk and a worry because there is relentless opposition that can muster a lot of traction.”

Late Wednesday afternoon, Premier Jason Kenney voiced similar concerns, calling the

U.S. decision a gut punch to the Alberta economy.

If the American administra­tion won't sit down and have further dialogue about the pipeline, Kenney said Prime Minister Justin Trudeau should impose “meaningful trade and economic sanctions in response.”

The premier reiterated his concerns a retroactiv­e cancellati­on of the KXL permit that was signed off by former president Donald Trump will set a precedent that could be imposed on other pipelines.

“There are people now working in the White House who I believe may very well counsel the president to use on other pipelines the power that he used today,” said Kenney, whose government has invested $1.5 billion in Keystone XL.

The decision to block it came as the Canadian energy sector was finally making progress on building pipelines to unclog bottleneck­s in the oil-transporta­tion system and improve returns for petroleum producers.

Aside from work on Keystone, constructi­on has also been underway on the Trans Mountain expansion and Enbridge's Line 3 replacemen­t project.

“It is a loss, it is problemati­c and it is significan­t, but there are alternativ­es,” said Tristan Goodman, president of the Explorers and Producers Associatio­n of Canada.

Killing Keystone XL was always going to be a highly political decision, given Biden's campaign promise to cancel the presidenti­al permit.

But it also highlights how vulnerable Canada remains with one major customer for its oil.

“The real issue Canada has to think about is just how durable is our long-standing, trustworth­y economic partnershi­p with the United States?” said Hal Kvisle, the former CEO of Transcanad­a Corp. (now TC Energy) when Keystone XL was first proposed in 2008.

With the developmen­t sidelined, attention turns to other pipelines, including Enbridge's Line 3 project and its existing Line 5 pipeline, which has encountere­d political opposition in Michigan.

“They are in more trouble than they were yesterday, that's for sure,” said Keith Stewart, senior energy strategist with Greenpeace Canada.

However, there are key difference­s.

While Keystone XL was a proposed developmen­t, the other projects are operating pipelines. Any changes to those lines would directly affect consumers, not just producers.

Line 3 will replace the older pipe in the ground and ship an additional 370,000 bpd of oil out of Western Canada to Superior, Wis., once it's completed in the fourth quarter of 2021.

Enbridge's Line 5 transports oil to refineries in Central Canada through Michigan.

The governor gave notice in November that the state intends to revoke a six-decade-old easement that allows the pipeline to cross the Straits of Mackinac, while Enbridge disputes its authority to do so.

All of this puts more pressure on the Trudeau government to make sure the Trans Mountain project gets built.

The pipeline to the B.C. coast from Alberta is one developmen­t that remains within the country's control, and it will allow for increased exports to customers in Asia.

What will Ottawa do next?

In an interview, Natural Resources Minister Seamus O'regan noted Biden had made a clear campaign commitment on Keystone XL, but acknowledg­ed he was “brutally disappoint­ed we didn't get the opportunit­y to make the case” for the project.

Asked if the decision increases the risk to other pipelines, O'regan stressed the new U.S. administra­tion is filled with pragmatic and “entirely predictabl­e people.”

“We are their biggest supplier, they are also our bigger customer. So managing this relationsh­ip and getting it right is vital not just to us, it's vital to them, as well.”

 ??  ??

Newspapers in English