Edmonton Journal

Alberta AG urges procuremen­t process revamp

Wylie recommends better controls for infrastruc­ture project contracts

- ASHLEY JOANNOU ajoannou@postmedia.com twitter.com/ashleyjoan­nou

Alberta's auditor general has made a series of recommenda­tions for improvemen­ts he says are needed to ensure the procuremen­t process for government infrastruc­ture projects is more effective.

In a report released Wednesday, auditor general Doug Wylie said some procuremen­t documents are not being posted for the required length of time, the old process confirming that only bids submitted on time are evaluated did not operate effectivel­y and that the government does not have adequate controls to verify that bids comply with requiremen­ts.

“Constructi­on contracts are often in the millions of dollars. Proponents invest time and money in the developmen­t of their submission­s, including their bids, and they rely on and expect fair and competitiv­e procuremen­t processes,” Wylie said in a statement.

“Albertans should be confident that Alberta Infrastruc­ture has effective processes to ensure the significan­t dollars it spends on constructi­on contracts are procured fairly and competitiv­ely.”

As part of the informatio­n gathered from August 2021 to March 2022, auditors found nine out of 17 sampled requests for qualificat­ions (RFQS) — each with an estimated value of more than $9.1 million — had not been posted for the minimum 25 days required by the trade agreements. Alberta Infrastruc­ture posted three of the 17 RFQS for only 14 days.

According to the report, Alberta Infrastruc­ture receives 17 per cent of bid submission­s within one minute of the procuremen­t closing. Auditors found that bid forms were not always accurate and that Alberta Infrastruc­ture accepted hard copy bids that were late before it changed its process to only accepting electronic submission­s.

Alberta Infrastruc­ture does not have adequate controls to verify that bids comply with requiremen­ts, Wylie said

According to the report, in eight of the 58 procuremen­ts sampled, the bid bond was not issued correctly because the proponent did not use Alberta Infrastruc­ture's legal name. Those bonds are usually disqualifi­ed because there's a risk that they may not be enforceabl­e. However, in these cases only one was disqualifi­ed.

“In one case, Alberta Infrastruc­ture awarded a contract with a value between $5 million and $10 million to a proponent with an improperly issued bond,” the report says.

In another case, the request for proposals included a requiremen­t that bids not be over a certain amount. Each submitted bid was too high but no one was disqualifi­ed.

“The contract went to the lowest bidder. A risk exists that the competitio­n may have been limited if some proponents did not bid on the project as they may have anticipate­d their bid would exceed the maximum amount stated in the RFP,” the report says.

In the end, Wylie recommende­d the government put in better controls to ensure compliance with trade agreements as well as improvemen­ts for receiving and evaluating submission­s.

“Based on our audit criteria, we conclude that Alberta Infrastruc­ture has processes to ensure fair and competitiv­e procuremen­t of its constructi­on tenders but not all of these processes are effective, and improvemen­ts can be made,” he said.

In a statement, Brendan Procé, director of communicat­ions for Alberta Infrastruc­ture, said the department has already implemente­d or improved many of the processes that the audit identified.

“We accept the OAG'S recommenda­tions and are working to explore, enhance and further develop our constructi­on procuremen­t processes to ensure our systems remain fair, open and transparen­t,” he said.

 ?? JASON FRANSON/ THE CANADIAN PRESS ?? Alberta auditor general Doug Wylie says that Albertans should be confident in the province's process for procuremen­t.
JASON FRANSON/ THE CANADIAN PRESS Alberta auditor general Doug Wylie says that Albertans should be confident in the province's process for procuremen­t.

Newspapers in English

Newspapers from Canada