CONFEDERATION bridge
Timeline Nov. 16, 1987
– Ottawa calls for proposals for construction of a fixed link between N.B. and P.E.I.
Jan. 18, 1988
– P.E.I. holds Plebiscite.
Sept. 30, 1988
– Ottawa identifies 3 successful bidders to submit prices
July 17, 1992
– Strait Crossing Development Inc. (SCDI) submits lowest bid
Sept. 29, 1993
– Deal reached between Ottawa and SCDI
Oct. 8, 1993
– First site clearing of fabrication yeard
Sept. 1994
– Concrete poured for first bridge component
April 1995
– Crane places first bridge segment
June 1995
– Last attempt by project’s opponents fails in federal court
Aug. 1995
– First pier is erected
Aug. 3, 1996
– Bridge reaches halfway point
Sept. 27
– Bridge named announced
Nov. 19, 1996
– P.E.I. and New Brunswick joined for first time
May 31, 1997
– The Confederation Bridge opens