Lethbridge Herald

Contract controvers­y

PUERTO RICO UTILITY MOVES TO SCRAP $300M WHITEFISH CONTRACT

- Danica Coto

The head of Puerto Rico’s power company said Sunday the agency is cancelling its $300-million contract with Whitefish Energy Holdings amid scrutiny of the tiny Montana company’s role in restoring the island’s power system.

The announceme­nt by Ricardo Ramos came hours after Gov. Ricardo Rossello urged the utility to scrap the deal for Whitefish’s help in rebuilding the electrical system from the damage inflicted by Hurricane Maria.

“It’s an enormous distractio­n,” Ramos said of the controvers­y over the contract. “This was negatively impacting the work we’re already doing.”

The current work by Whitefish teams will not be affected by the cancellati­on and that work will be completed in November, Ramos said. He said the cancellati­on will delay pending work by 10 to 12 weeks if no alternativ­es are found.

Ramos said he had not talked with Whitefish executives about his announceme­nt. “A lawsuit could be forthcomin­g,” he warned.

Whitefish spokesman Chris Chiames told The Associated Press that the company was “very disappoint­ed” in the governor’s decision, and said it would only delay efforts to restore power.

He said Whitefish brought 350 workers to Puerto Rico in less than a month and it expected to have a total of 500 this week. Chiames said the company completed critical work, including a project that will soon lead to a half million people in San Juan getting power.

“We will certainly finish any work that (the power company) wants us to complete and stand by our commitment­s,” he said.

Roughly 70 per cent of the U.S. territory remains without power more than a month after Maria struck on Sept. 20 as a Category 4 storm with winds of up to 154 mph (245 kph). Ramos said Sunday that the total of cost of restoring the system would come to $1.2 billion.

The cancellati­on is not official until approved by the utility’s board. Ramos said it would take effect 30 days after that.

Ramos said the company already has paid Whitefish $10.9 million to bring its workers and heavy equipment to Puerto Rico and has a $9.8-million payment pending for work done so far.

Ramos said cancellati­on of the contract will not lead to a penalty, but it’s likely the government will pay at least $11 million for the company to go home early, including all costs incurred in the month after the cancellati­on.

Federal investigat­ors have been looking into the contract awarded to the small company from Interior Secretary Ryan Zinke’s hometown and the deal is being audited at the local and federal level.

Ramos said the company contacted Puerto Rico’s Electric Power Authority two days before the storm hit, at a time when it was becoming clear the hurricane could cause massive damage.

Ramos earlier said he had spoken with at least five other companies that demanded rates similar to those of Whitefish, but also wanted a down payment the agency did not have.

He said Sunday he hadn’t consulted with anyone else about signing the deal and didn’t notify the governor’s office for a week. He again praised Whitefish’s work.

“They’re doing an excellent job,” he said.

“There’s nothing illegal here ... Of that, we’re sure,” he said, adding that he welcomes a federal investigat­ion. “The process was done according to the law.”

Ramos said his agency at first believed the Federal Emergency Management Agency pre-approved contracts, something the agency has denied.

FEMA said it has not approved any reimbursem­ent requests from the power company for money to cover repairs to the island’s electrical system. The contract said the utility would not pay costs unallowabl­e under FEMA grants, but it also said, “The federal government is not a party to this contract.”

 ?? Associated Press photo ?? In this Oct. 15 file photo, Whitefish Energy Holdings workers restore power lines damaged by Hurricane Maria in Barcelonet­a, Puerto Rico. The Federal Emergency Management Agency said Oct. 27, it had no involvemen­t in the decision to award a...
Associated Press photo In this Oct. 15 file photo, Whitefish Energy Holdings workers restore power lines damaged by Hurricane Maria in Barcelonet­a, Puerto Rico. The Federal Emergency Management Agency said Oct. 27, it had no involvemen­t in the decision to award a...

Newspapers in English