National Post

Emissions cap lacking, Green groups say.

- Jesse Snyder

• Environmen­tal groups lined up against Ottawa’s decision to approve the Pacific NorthWest LNG export terminal, saying some of the conditions imposed don’t go far enough to reduce carbon emissions in the province.

On Tuesday the Canadian Environmen­tal Assessment Agency (CEAA) approved the project with 190 conditions, including a hard cap on total carbon emissions from the facility and a reduction in emissions intensity based on pertonne output of the terminal. However, critics say the stipulatio­ns still leave the project well above the carbon footprints of other LNG proposals, as the consortium does not plan to use off-site electricit­y to power the facility.

“I don’t see the conditions on carbon as being a particular challenge,” said Matt Horne of the Pembina Institute, an environmen­tal organizati­on. “They don’t seem particular­ly binding.”

The project was proposed in 2012 by a consortium led by Petronas, a Malaysian company. It aims to build the terminal near Prince Rupert, B.C., and would export up to 1.7 billion cubic feet of liquefied natural gas per day to overseas markets.

Various environmen­tal groups have come out against Pacific NorthWest and other LNG facilities, arguing they leave too large an environmen­tal footprint for the province to meet its climate goals.

As part of the approval of Pacific NorthWest, the CEAA capped total carbon emissions from the facility at 4.3 million tonnes, about 20 per cent below the level proposed by the consortium.

Emissions intensity on a per- tonne level must also be reduced to 0.21 tonnes of CO2 equivalent for every tonne of LNG produced for the third liquefacti­on unit, down from an earlier proposal of 0.22. Those limits for both emissions intensity and total emissions depend on whether the company decides to build a third liquefacti­on unit, sometimes called “trains” within the industry.

Reducing per-tonne emissions could potentiall­y prove particular­ly onerous for the Pacific NorthWest, says Raymond James analyst Andrew Bradford, considerin­g 0.22 was at the low end of the company’s earlier estimates.

“They’re asking for an improvemen­t for the potential third train from what appears to be, to my eyes, the current state of the art,” he says.

Emissions intensity from the Pacific NorthWest facility is higher than other proposals largely because it will use natural gas- fired power turbines rather than electricit­y.

LNG Canada, an LNG export facility led by Royal Dutch Shell PLC, planned to draw electricit­y from B.C.’s clean electricit­y grid and would have achieved an emissions intensity of 0.15 tonnes of CO2 for every tonne of LNG produced, according to public filings. The project was put on hold in July of this year.

Pacific NorthWest has been pressured by environmen­tal groups to electrify a portion of its operations, but the company has said is not feasible because it would require the company to build long- distance transmissi­on lines to reach its remote location. The project would be located near Prince Rupert, B.C.

It also said in an applicatio­n to provincial authoritie­s that there was a “lack of available electricit­y to supply the plant in the Project’s timeline.”

David Austin, an associate counsel at Clark Wilson LLP in Vancouver, says BC Hydro’s latest load forecast appears to support that contention, as it doesn’t include nearly enough new capacity to power numerous LNG export facilities. The B. C. government has long touted electrific­ation in both upstream and downstream operations as a way to limit the emissions linked to LNG developmen­t.

Environmen­tal groups like Pembina and others say that without significan­t electrific­ation of the facility, the project could set back British Columbia’s climate goals.

“We had argued that for the third train of production electrific­ation should be part of the conversati­on,” Horne said. “That would give them time to figure out the transmissi­on issues.”

The consortium did not respond to a phone call but said in an emailed statement it plans to “conduct a total project review over the coming months prior to announcing next steps for the project.”

The consortium’s other partners include Japan Petroleum Exploratio­n Co., Indian Oil Corp., China Petroleum & Chemical Corp. and Brunei National Petroleum Co.

 ?? DARRYL DYCK THE CANADIAN PRESS ?? An aide, left, directs members of the Tsimshian First Nation at the PNW approval announceme­nt on Tuesday.
DARRYL DYCK THE CANADIAN PRESS An aide, left, directs members of the Tsimshian First Nation at the PNW approval announceme­nt on Tuesday.

Newspapers in English

Newspapers from Canada