Michigan looks at options to address spill risk

-

CALGARY• Michigan has released a report looking at how to deal with the spill risk of Enbridge’s Line 5 pipeline that runs exposed underwater in a strait between Lake Huron and Lake Michigan.

The report Thursday by Dynamic Risk Assessment Systems found that building new pipelines around the Great Lakes would cost between US$ 2 billion and US$ 4 billion depending on the route. Barges and trucks were discounted as options because of the logistical constraint­s of trying to handle the 86 million litres of petroleum products per day currently shipped on the line.

An anchor catching the pipeline was identified as the most likely cause of a spill. The report said replacing the exposed 1953 pipeline with a US$ 30- million underwater trench or US$ 150- million tunnel for the more than sixkilomet­re crossing would either minimize or make negligible the risks to the line.

Shutting down the pipeline would lead to disruption­s for Enbridge and the refineries it supplies, with the report estimating Michigan residents would pay $121 million a year more for gasoline and other refined products, while Enbridge would be on the hook for $212 million in abandonmen­t charges.

The report estimates that the cost of a spill would run between US$100 million and US$ 200 million. Modelling showed a spill on average would affect about 32 kilometres of shoreline.

Enbridge said in a statement that it remains committed to protecting the Great Lakes, but needs time to review and assess the findings before making specific comments.