Suncor files to build new oilsands project

- GEOFFREY MORGAN Financial Post gmorgan@nationalpo­st.com

CALGARY • Suncor Energy Inc. has filed an applicatio­n for a massive new oilsands project defying expectatio­ns of slowing growth in the oilsands.

The Alberta Energy Regulator issued a notice Tuesday that Suncor is seeking regulatory approval to build a 160,000- barrels- per- day steam- based oilsands project north of Fort McMurray called Lewis. The project would not require federal approval from the National Energy Board, which Ottawa is currently reorganizi­ng.

Regulatory filings from Calgary- based Suncor show the project – which would be built in four identical 40,000- bpd phases – would cost $6.2 billion in total and the company hopes to begin constructi­on in 2024, with oil production starting 2027.

“This is a growth project,” Suncor spokespers­on Erin Rees said in an email, adding the company has not officially sanctioned the project.

In its applicatio­n, Suncor said the project would contribute almost $ 3.4 billion to Alberta’s GDP and employ an average of 580 constructi­on workers per year and 1,000 constructi­on workers at its peak it 2027 and 2028.

The permit will help Suncor plan its next projects to replace the production that will end in the 2030s, according to one analyst.

“The life- of- mine plans show production ending. It’s so far away that nobody really thinks about it, but it’s probably a decade of planning,” GMP FirstEnerg­y analyst Michael Dunn said of the mine retirement.

He said Suncor is looking at ways to boost production so that its oilsands upgrading facilities — vital for the company to get a higher price for its bitumen — will continue to be fully utilized.

“All these things go into the decision- making,” Dunn said, adding that Suncor will need to look at replacing its production from its base mine potentiall­y through lease swaps with Syncrude or through new projects.

The Lewis project’s time frame aligns with Suncor’s efforts to boost production ahead of the anticipate­d closure of the company’s main mining operation north of Fort McMurray in the early 2030 s. Suncor’s detailed mine plans, and the AER’s tailings plans, show the company’s primary mining operations will wrap up in 2033.

“With Suncor’s Oil Sands Base Plant approachin­g end of mine life ( 2033), the AER is concerned with the length of time remaining to resolve Suncor’s site-specific issues,” an AER report from October 2017 states. The AER approved Suncor’s plan to address those issues the regulator had identified.

Suncor produced 296,700 bpd from mining operations in the fourth quarter of 2017, which accounts for roughly 55 per cent of the company’s operated oilsands production with the balance coming from steam-based projects.

Suncor has also recently boosted its stake in the Syncrude oilsands mining venture to 58 per cent and is also ramping up production at its recently completed $ 17- billion Fort Hills project — neither of those projects will expire in the 2030s.

During an earnings call this month, Suncor CEO Steve Williams described the Lewis project — and the company’s Meadow Creek East and Meadow Creek West projects — as the next wave of growth for Suncor, beginning at the end of 2022. “You will start to see one of those come on every 12 to 24 months,” Williams said.

At the time, he said those “replicatio­n” projects would drive growth for Suncor rather than investment in major new projects and blasted Canada’s current regulatory and tax framework as being too burdensome for major projects.