Defence wants early start on naval resupply ships

Would see first ship delivered in about 4 years

-

OTTAWA• The Department of National Defence wants to get an early start on cutting steel for the navy’s new support ships, hoping to keep the multibilli­on- dollar project from slipping farther behind schedule.

The plan would see some work on the two support ships begin in Vancouver later this year, taking advantage of a lull in the constructi­on of two science vessels for the Canadian Coast Guard.

While the science vessels would still be delivered first, officials are hoping the head start will prevent another 12- month delay to the Protecteur- class joint support ships, as the naval vessels are officially known.

Defence officials are now talking to counterpar­ts from other federal department­s about the plan, which was initially pitched by Seaspan Shipbuildi­ng in Vancouver.

Seaspan is responsibl­e for building the two Protecteur-class vessels as well as four science ships and a polar icebreaker for the coast guard.

“The final shipyard proposal for the constructi­on of the joint support ships will be presented for government approval in the coming year,” Defence Department spokesman Daniel Le Bouthillie­r said in an email.

“Discussion­s are underway on an early start to constructi­on of the ships in 2018. This would result in the delivery of the first ship in about four years, with the second ship being delivered one year later.”

The plan is the latest twist in what has been a decadelong odyssey to equip the military with new support vessels, which are considered some of the most essential ships for a modern navy.

Canada has been without a permanent support ship since 2015, when the navy was forced to retire its existing vessels due to a fire aboard one and corrosion aboard the other.

The gap will get a little smaller Tuesday when the navy formally welcomes to the fleet the converted civilian freighter MV Asterix, which will be leased to the government for five years, with a five-year option.

Navy commander Vice-Admiral Ron Lloyd was set to participat­e in a ceremony Tuesday in Halifax, after which the Asterix is expected to participat­e in a major U.S.led exercise before heading to Asia.

But defence officials have said Asterix, owned by Quebec- based Davie Shipyards, won’t be deployed into harm’s way and is not a true military vessel like the Protecteur-class — an assertion Davie has refuted.

“This ship has a robust force protection capabil- ity for when it deploys outside of Canadian waters,” said Spencer Fraser, head of Davie’s sister company, Federal Fleet Services. “So to say the ship is defenceles­s is a complete exaggerati­on and misnomer.”

Constructi­on on the first support vessel was supposed to start in 2016, with delivery slated for 2019. But the project has been plagued by delays and cost uncertaint­y; the government says its $2.3-billion budget is also under review.

The most recent concern was a warning from Seaspan that it might have to lay off workers during a gap in constructi­on between the third and fourth science vessels, which are completely different designs.

That prompted fears that experience­d workers would move to other shipyards and be unavailabl­e when it came time to ramp up production on the last science vessel and the support ships.

Starting some work on the support ships would prevent layoffs, said Seaspan vicepresid­ent Tim Page. It would also keep the scheduled delivery of the support ships to 2022 and 2023, rather than 12 months later.

“This opportunit­y will support the needs of our navy customer and enable us to retain the shipbuildi­ng knowledge and experience of our workforce,” Page said in an email.

 ?? DARRYL DYCK / THE CANADIAN PRESS FILES ?? Workers watch as the main girder of a new 300-tonne gantry crane is lifted into place at Seaspan in Vancouver.
DARRYL DYCK / THE CANADIAN PRESS FILES Workers watch as the main girder of a new 300-tonne gantry crane is lifted into place at Seaspan in Vancouver.