National Post (National Edition)

Billions in resource spending lost: report

- Geoffrey Morgan

CALGARY • A new report shows $100 billion in planned spending on resource projects in Canada has evaporated, and a further drop should be expected without substantia­l amendments to the Liberal government’s planned regulatory overhaul in Bill C-69.

As Senate hearings into the controvers­ial bill continued Thursday, the C.D. Howe Institute released a report detailing how recent declines in planned energy, mining and forestry investment in Canada totalling $100 billion is equivalent to erasing 4.5 per cent from Canada’s gross domestic product.

Trans Canada Corp.’ s $15-billion Energy East pipeline, CNOOC Ltd.’s Aurora LNG and Petronas Bhd’s $36-billion Pacific NorthWest LNG project are among the major resource projects that have been cancelled in recent years after long and uncertain regulatory processes, contributi­ng to the $100-billion figure.

The declines in planned investment in Canada’s resource sector have continued even as investment­s in competing jurisdicti­ons have rebounded following a years-long decline in commodity prices, C.D. Howe Institute associate director of research and co-author of the report Grant Bishop said.

“U.S. and global investment in oil and gas has rebounded while in Canada it has continued to plunge,” Bishop said, adding, “Global planned investment in mining has dropped but it has dropped further in Canada.”

Industry groups across the resources sector including the Canadian Energy Pipelines Associatio­n and the Mining Associatio­n of Canada are asking the Senate to amend the bill. Other think tanks, including the Canada West Foundation, have also called for substantia­l changes to the bill.

Part of the issue is long regulatory timelines. The study shows it can take up to 15 years to get a mine approved in Canada, compared with six years in Australia. Or it can take up to 11 years for pipeline approvals in Canada, compared with two years in Australia or five years in the U.S.

More important, he said the bill and regulatory overhaul does not fix the biggest obstacle facing major resource projects: the federal government’s own approach to consultati­ons with Aboriginal people affected by developmen­t.

“The critique is that Bill C-69 is being pitched as being necessary to fix major resource projects,” Bishop said. “The legislatio­n is not addressing the problem that has tripped up major resource projects.”

Approvals for the Trans Mountain pipeline expansion project, for example, were overturned in Aug. 2018 when the Federal Court of Appeal found Ottawa did not properly consult with affected First Nations.

The Appeals Court judge found that the third phase of Ottawa’s consultati­on consisted primarily of note-taking rather than a meaningful dialogue, which is similar to the issue that caused the same court to overturn appeals for Enbridge Inc.’s Northern Gateway approvals in June 2016.

Bishop said Bill C-69 will not change anything about the regulatory process that would have resulted in different outcomes for either Northern Gateway or Trans Mountain, as it doesn’t update the federal government’s consultati­on guidelines.

The last time those guidelines were updated was 2011, before either of those pipeline decisions were rendered.

Those guidelines were based in part on interim guidelines developed in 2008 following Supreme Court of Canada decisions from 2004 and 2005.

Natural Resources Minister Amarjeet Sohi did not respond to a request for comment.

In response to the Appeals Court decision on Trans Mountain, Sohi asked the National Energy Board to provide a new review of the project and launch fresh consultati­ons with affected First Nations. The board is expected to release its findings on Friday.

Newspapers in English

Newspapers from Canada