Ottawa Citizen

Pandemic could provoke ‘force majeure’ in Phase 2

Pandemic might provide severe test for light-rail expansion project timeline

- JON WILLING

The COVID-19 pandemic could test the strength of city contracts when unfathomab­le obstacles threaten huge projects, such as the big Stage 2 expansion.

Major constructi­on contracts typically have “force majeure” clauses that provide potential escape hatches for vendors unable to work under extraordin­ary and unavoidabl­e scenarios.

Since the pandemic and government-mandated restrictio­ns have impacted almost every aspect of profession­al and personal lives, the force majeure parts of contracts are potentiall­y in play as a way to possibly give contractor­s relief from constructi­on schedules. It’s a hot topic in the procuremen­t industry.

The two Stage 2 contracts, which authorize $4.6 billion of work to expand the Confederat­ion Line and Trillium Line, have clauses that define five force majeure scenarios. They broadly speak to war, radioactiv­e contaminat­ion, chemical or biological contaminat­ion, pressure waves and discovery of important species-at-risk, fossils and artifacts.

The city has heard from Stage 2 contractor­s that they’re monitoring the effects of the pandemic on constructi­on.

Constructi­on of the Trillium Line expansion has a contracted ending of August 2022, with the northsouth railway still scheduled to be closed for about two years starting on Sunday.

The eastern leg of the Confederat­ion Line is scheduled to be done in November 2024 and constructi­on of the western leg is scheduled to be done in May 2025.

The most recent informatio­n from city hall is that force majeure clauses haven’t been activated by contractor­s.

“We’ve talked to our lawyers in terms of whether someone can request or claim a force majeure but we have not been formally advised by any of our contractor­s that that, in fact, is what they’re planning to notify us of,” city manager Steve Kanellakos said during a press conference last Wednesday.

However, Kanellakos said the Stage 2 contractor­s are concerned about their timelines, especially because supply chains have been impacted by the pandemic.

With the Stage 2 constructi­on scheduled to last several years, particular­ly on the LRT portion, the contractor­s believed they can make up any lost time along the way, Kanellakos said.

“We don’t have anything from them formal, saying that they want us to adjust the timelines or declaring anything under the contract looking for relief, but they have signalled to us that it’s a watch item for them,” Kanellakos said.

“Like all these things, it depends how long this goes on and how the economy starts opening up,” Kanellakos said.

When the World Health Organizati­on confirmed a global pandemic in March, talks started heating up in the procuremen­t industry about how contracts would be impacted.

An online chat hosted by Supply Chain Canada had legal experts answer questions from industry profession­als; it was so popular that experts Debby Shapero Propp and Marvin Huberman will be answering questions during another online chat this week.

Huberman, a chartered arbitrator and certified constructi­on adjudicato­r based in the Toronto area, described the buzz around force majeure issues as “white-hot” in procuremen­t circles.

“They’re getting a whole bunch of reasons ultimately flowing from the COVID-19 pandemic that parties, including the City of Ottawa and those involved in contracts with it, try to understand whether or not you use this situation to invoke a force majeure clause or excuse contractua­l non-performanc­e,” Huberman said.

The answer isn’t straightfo­rward, since it depends on language in the contracts, how the language is interprete­d, the applicatio­n of the law and the evidence supporting a claim of force majeure, Huberman said. Even if a contract doesn’t have a force majeure clause, a party might look at other laws to see if they provide contract relief, he noted.

Huberman predicted there will be a “tremendous number of cases being brought for arbitratio­n and also in the courts” within a year or two related to contracts and the impact of COVID-19. jwilling@postmedia.com twitter.com/JonathanWi­lling

Newspapers in English

Newspapers from Canada