Ottawa Citizen

Science-ship project cost sails up

Expected bill for federal vessel rises nearly tenfold since 2008

- DAVID PUGLIESE

The cost of building an offshore science vessel for the federal government, originally set at $108 million, has jumped to almost $1 billion.

The estimate for the project had been steadily climbing, from $108 million in 2008 to $144 million in 2011 and then to $331 million, according to federal government figures.

But on Feb. 18 the cost to taxpayers for the offshore oceanograp­hic science vessel — or OO SV project — took its steepest jump yet with new figures showing it had climbed to $966.5 million.

South Africa is constructi­ng a similar oceanograp­hic vessel with an ice-strengthen­ed hull in a project with a budget of around $170 million.

Retired Liberal senator Colin Kenny, the former chairman of the senate defence committee, said the significan­t jump in cost of the Canadian-built oceanograp­hic vessel is staggering. “Why isn't anyone in government saying that this type of expense is crazy and it's time to put an end to this level of expenditur­e for a single ship,” Kenny said.

But Barre Campbell, spokesman for Fisheries and Oceans Canada and the Canadian Coast Guard, noted in an email, that the original budget was set based on the best data and methods at the time. “As the project has progressed and moved closer to constructi­on, the estimated project cost has been updated to reflect the value of negotiated contracts and actual costs incurred,” he added.

The cost has been reviewed by independen­t experts, Campbell added.

Constructi­on of the OOSV at Seaspan shipyards in Vancouver is expected to begin shortly. The vessel will be delivered in 2024. Seaspan has already received around $280 million over the past six years to work on the design and other elements of the OOSV, according to informatio­n presented to Parliament.

For major projects such as the OOSV, contracts are generally longer, which can cause an increase of cost drivers such as inflation, labour rates, commodity prices, engineerin­g, spare parts, insurance and warranty, Campbell added.

But in December 2011, a team of auditors warned Fisheries and Oceans and the Coast Guard that they had failed to adopt a strategy to deal with constructi­on delays for the vessel.

“By not developing adequate risk mitigation strategies for time delays, the Canadian Coast Guard is vulnerable to higher-than-anticipate­d costs and ineffectiv­e delivery of programs,” the independen­t auditors hired by the federal government said.

The auditors also noted that the procuremen­t staff overseeing the acquisitio­n of the OOSV had erroneousl­y concluded the project was “low risk.”

The OOSV will be outfitted with equipment for marine and scientific research on ocean currents and the seabed. It will replace an existing Canadian Coast Guard science research ship. The new vessel will be capable of performing multiple tasks, including oceanograp­hic, geological and hydrograph­ic survey missions. This work will contribute to Canada's understand­ing of oceans and the impacts of climate change, the federal government says.

The OOSV is being built as part of the federal government's National Shipbuildi­ng Strategy. Auditor General Karen Hogan is currently examining that strategy, with a report to be released Feb. 25.

The day before that audit is released, Parliament­ary Budget Officer Yves Giroux will make public his study on the cost of another shipbuildi­ng strategy program, the Canadian Surface Combatant. That project to buy 15 new warships has also skyrockete­d in price.

The Canadian Surface Combatant project would see the constructi­on of Type 26 warships for the Royal Canadian Navy at Irving Shipbuildi­ng on the East Coast. The vessels will replace the current Halifax-class frigate fleet. However, the project has already faced delays and significan­t cost increases in cost, from an original $14-billion estimate to $26 billion and then to $70 billion.

The PBO study comes at the request of the House of Commons government operations committee, which wanted to get the latest cost figures on the surface combatant project.

The Department of National Defence revealed Feb. 1 that the delivery of the first ship would be delayed until 2030 or 2031. It was to have been delivered in 2025, according to DND documents. The five-year delay is expected to cost taxpayers billions of extra dollars.

Newspapers in English

Newspapers from Canada