Regina Leader-Post

Sask. presses Ottawa to share $268M cost of Gunnar mine remediatio­n

- ALEX MACPHERSON amacpherso­n@postmedia.com twitter.com/macpherson­a

SAKSATOON Saskatchew­an taxpayers could be left holding a quarter-billion-dollar bill if provincial officials can’t convince the federal government to honour a 12-year-old pledge to pay half the cost of cleaning up an abandoned uranium mine near the Northwest Territorie­s border.

The provincial government has now sunk $102 million into the $268 million project, the cost of which has ballooned to 10 times the original estimate. Ottawa, meanwhile, won’t commit any more than the $12.3 million it pledged when the project began 12 years ago.

“We continue to urge the federal government to contribute more money to this cost shared project. Discussion­s are continuing,” Saskatchew­an government spokesman James Parker said this week in an email.

Natural Resources Canada, meanwhile, contends the massive cost overrun is a provincial responsibi­lity because the Gunnar mine site is owned by the Saskatchew­an government. Both the federal and provincial government turned down interview requests.

Gunnar Mining Ltd. built the mine on a peninsula jutting into Lake Athabasca, about 800 kilometres north of Saskatoon, and operated it from 1955 to 1963. The mine, its open pit flooded with water, was abandoned and the company dissolved the following year.

More than four decades later, the provincial and federal government­s agreed to split the estimated $24.6 million cost of cleaning up the site, a project that included tearing down buildings filled with asbestos and covering radioactiv­e tailings and waste rock piles with earth.

A memorandum of agreement signed in 2006 stated both parties must discuss the financing of any additional or unforeseen costs. Parker said cost overruns were expected, and the province will continue to urge Natural Resources Canada to honour the original deal.

“In the late 1950s when these mines were developed, the federal government exerted significan­t influence on uranium developmen­t in Canada and all production was required to be sold through the federal Crown corporatio­n Eldorado Mining and Refining Ltd.,” he said.

Despite saying it places the “highest priority” on environmen­tal protection, the federal ministry has committed only to paying the remaining $11.1 million once final approvals for the remediatio­n work are issued by provincial and federal regulators.

“The Saskatchew­an government is the owner of the Gunnar site and is responsibl­e for developing remediatio­n plans, funding and management of the remediatio­n project,” spokeswoma­n Jocelyn Argibay said in an email.

The province’s argument that Ottawa should be partly responsibl­e for the cost because it had a monopoly on exports has previously been made by provincial and federal politician­s, as well as the Saskatchew­an Environmen­tal Society, which said Ottawa’s position did not seem reasonable.

NDP MP Georgina Jolibois, whose Desnethé—Missinippi— Churchill River constituen­cy encompasse­s the abandoned mine, said Wednesday it is the responsibi­lity of both the federal and provincial government­s to clean up the site, as both profited from its existence.

Asked whether the provincial government will be able to extract more cash from Ottawa and avoid leaving Saskatchew­an taxpayers footing the bill, Jolibois replied: “With enough pressure, there’s always a possibilit­y.”

Remediatio­n work at the mine is expected to wrap up in 2021 or 2022, at which point the project will enter a longer-term monitoring phase.

Newspapers in English

Newspapers from Canada