The Guardian (Charlottetown)

Good progress on Queens Arms intersecti­on work, says city

-

A 160-tonne crane is expected to arrive Sunday to assist in the constructi­on project at the Queens Arms intersecti­on in Charlottet­own.

The machine will start moving large concrete box sections into a prepped trench on Monday. The project, being done where Capital Drive, North River Road and Lower Malpeque Road meet, is to replace a storm channel, which the City of Charlottet­own says must be completed to prevent the road from collapsing.

The work started on Monday and was expected to take two weeks.

The city said Friday it was pleased with the progress made one week into the project.

Contractor­s have been excavating and the trench was expected to be completed by Friday.

Constructi­on is currently on schedule. The weather has cooperated and it will play a big part in progress and the work scheduled for next week.

The city said traffic has flowed relatively well and detour routes are being used.

The project has compounded queues on streets around the constructi­on area, so changes have been made to normal traffic signal timings in order to clear most lineups with each cycle.

Drivers on detour routes are reminded that those streets are seeing heavier than normal traffic and courtesy is appreciate­d for those trying to enter or exit at non-signalized intersecti­ons and driveways.

The contractor had hoped to keep some sidewalk access open, but now that a major excavation is underway, there will be no pedestrian access through the intersecti­on due to safety concerns.

It is anticipate­d there will not be pedestrian access at the intersecti­on until the project is almost complete.

Businesses in the area of the intersecti­on have remained open and local traffic has been, and will continue to be, permitted through to those businesses.

For more informatio­n, www.charlottet­own.ca. visit:

 ?? SUBMITTED PHOTO ?? A trench has been dug diagonal through the intersecti­on of North River Road in Charlottet­own in preparatio­n for the large concrete box sections being moved into the trench early next week.
SUBMITTED PHOTO A trench has been dug diagonal through the intersecti­on of North River Road in Charlottet­own in preparatio­n for the large concrete box sections being moved into the trench early next week.

Newspapers in English

Newspapers from Canada