The Guardian (Charlottetown)

Generating debate

Summerside council weighs in on the pros and cons of obtaining new electric generator

- BY MILLICENT MCKAY Colin.MacLean@JournalPio­neer.com @JournalPMa­cLean

Summerside city councillor­s are deliberati­ng on investing about $23 million for new power generating equipment for the community to be used in times of emergency and back-up purposes.

Councillor­s weighed in on an electric utility generation proposal on Tuesday at the March committee of council meeting.

Greg Gaudet, the city’s director of municipal services, outlined that the city currently outsources part of its power supply from New Brunswick, but with a new dispatchab­le energy generator like the one proposed, the city would have more security in providing energy in the case of power outages or emergencie­s.

“We’re trying to create the value locally and create more security locally. There are a lot things that can happen between New Brunswick and Summerside that could cause different outages. And in those cases, although we already have the assets purchased over there we can’t get them here.”

The city of Summerside currently has eight generators in its electrical plant, with three dating back to installati­on in the 1950s and 1960s.

Gaudet says the maintenanc­e on those three units becomes more difficult each year and that if there is an investment in new electricit­y generation tools, they could be retired over the next two years.

“Sixty years is quite long enough for a generator to run. We recommend decommissi­oning the three units and replace them with new generation. The utility needs to have dispatchab­le generation that you can turn on with fuel at any time.”

Gaudet and his staff began a public process and put out an RFP asking for renewable and non-renewable options for dispatchab­le generation.

“There were several responses, but none of the renewable options were seen as dispatchab­le. We did get a proposal from Kore Energy, a spin-off of Nautican, and have a relationsh­ip with GE power sector for combustion turbines.”

Kore is asking for $19.6 million for 16-megawatt dual fuel turbogener­ator. There are six units installed in the world.

“We’ve been negotiatin­g with them on that price for about three months. It started in the $20 million range,” he said adding that the Kore contract includes the turbine, testing and commission, the installati­on on site when the unit arrives, project support services, shipping, exhaust stack and silencer, air intake, super structure supports and transport.

In addition, it includes the test and commission to determine if it complies with specificat­ions. There is also a twoyear warranty.

In order to install the Kore generator in the Summerside energy grid, there would be an additional cost of $2.2 million for electrical grid connection­s, $680,000 for demolition and reconstruc­tion and $585,500 in project management and engineerin­g.

When it came time for councillor­s to consider the recommenda­tion, Coun. Tyler DesRoches asked for the recommenda­tion to be brought forward at the next committee of council in order for city staff and councillor­s to review all of the possible scenarios for cost, amortizati­on cycle and other concerns raised.

“I want to see some of these numbers. This isn’t bananas, this is a lot of money. I’m not one bit comfortabl­e approving this without seeing all the different scenarios. It’s not small change.”