The Hamilton Spectator

Randle Reef project enters new phase

This summer, contaminat­ed sediments will be dredged and placed inside a walled-off, rectangula­r section of the harbour that will eventually be capped

- MARK MCNEIL

THE SECOND PHASE of the massive $138.9-million Randle Reef remediatio­n project is set to begin as the multi-year project moves closer to being half completed.

Starting in mid-July and through the rest of this year and next, contaminat­ed sediment will be dredged and placed inside a walled off-area of the harbour, known as the Engineered Containmen­t Facility, which was constructe­d as part of the first phase of the project.

The enclosure — that encapsulat­es a 6.2-hectare area (about the size of seven football fields) — will ultimately be capped over and used for docking facilities. The facility has a double steel wall — with rock in-between — constructe­d around a section of the harbour where sediments are most contaminat­ed with polycyclic aromatic hydrocarbo­n (PAH) and heavy metals.

Now, less contaminat­ed material from around the site will be dredged and pumped into the facility.

“It’s basically like an underwater vacuum that vacuums the sediments into the facility. Then, the excess water is pumped into a treatment

facility where it is treated and pumped back into the harbour,” said Matt Graham, a sediment remediatio­n specialist with Environmen­t Canada.

The three-phase remediatio­n project comes 30 years after an Environmen­tal Canada scientist discovered a “black, oily, oozing mousse” while taking core samples from sediments near Stelco property in the harbour.

Later studies determined the area was a massive blob of coal tar, heavily contaminat­ed with PAHs and heavy metals that were constantly leaching into the water. Eventually a plan was drafted to contain, rather than remove the contaminan­ts.

Roger Santiago, head of the sediment remediatio­n unit at Environmen­t and Climate Change Canada, says “Phase 1 is wrapping up now. They have some welding work to take care of. That work is expected to be completed within the next two weeks. After that, they will spend the next month testing out the water treatment plant and the dredge.”

Last year, workers drove 33-metre sheet piles into the bay bottom forming a double wall in a rectangula­r shape.

High water levels complicate­d welding work, which is one of the reasons why some of the welding is being completed this summer.

By July, harbour watchers should see a floating dredge — and possibly second one — moving around Randle Reef, pumping sediments into the containmen­t facility through a large hose.

They’ll also see another hose drawing water from the facility into the treatment facility on land.

Santiago said the project is something that has never been done before.

“If you look at all of the components of what we are doing here, it is a first of its kind. Various parts have been done at other sites. But never all the parts together.”

 ?? JOHN RENNISON THE HAMILTON SPECTATOR ?? Matt Graham, a remediatio­n specialist with Environmen­t Canada, shows a Lego model of the Randle Reef project.
JOHN RENNISON THE HAMILTON SPECTATOR Matt Graham, a remediatio­n specialist with Environmen­t Canada, shows a Lego model of the Randle Reef project.
 ?? DAVID GRUGGEN SPECIAL TO THE HAMILTON SPECTATOR ?? Aerial photo of Randle Reef.
DAVID GRUGGEN SPECIAL TO THE HAMILTON SPECTATOR Aerial photo of Randle Reef.

Newspapers in English

Newspapers from Canada