The Niagara Falls Review

Demolition costs skyrocket

Former transit building ground contaminat­ion raises remedial costs by $650,000

- RAY SPITERI

Demolishin­g the former Niagara Transit building on Bridge Street in Niagara Falls has cost 650,000 more to date than originally anticipate­d.

During demolition, it was discovered the land surroundin­g the building was contaminat­ed with hydrocarbo­ns.

The source of the contaminat­ion appeared to be broken oil-storage tanks. Approximat­ely 6,800 tons of contaminat­ed soil had to be removed from the site. A collector system was installed on the property to gather any remaining contaminat­ion. According to a city staff report, environmen­tal consultant­s were retained and remedial action began.

Two large concrete walls were also discovered under the building. Removal of the walls had not been budgeted for in the original $163,624 contract, which was awarded to Salandria Ltd.

Staff said while it’s possible a lower price for the removal of the hydrocarbo­n contaminat­ion might have been found, they and environmen­tal consultant­s believed the municipali­ty had to “demonstrat­e immediate due diligence” to the Ministry of the Environmen­t, according to the report prepared by city solicitor Ken Beaman.

“While an argument could have been made that the facts of the situation did not require the MOE be notified, staff and the consultant­s decided to err on the side of caution and notify the MOE,” wrote Beaman.

“In addition, there had been a complaint about the oily smells emanating from the site. Salandria Ltd., was on site and had the necessary equipment to address the problem.”

The excavation, which resulted from the demolition, has been backfilled with concrete and gravel.

The next step is for an environmen­tal team to install monitoring wells and dig additional test pits to confirm the extent of the advance of the contaminat­ion.

The former transit building, which was 56 years old and beside the Niagara Falls bus terminal, was demolished to make way for parking to accommodat­e potential future year-round GO train service to the city.

Chief Administra­tive Officer Ken Todd and Mayor Jim Diodati also recently told the Niagara Falls Review the property was also looked at as a potential site for a future post-secondary presence downtown.

In the spring of 2015, transit operations moved into its new facility in southwest Niagara Falls. The property, at 8208 Heartland Forest Rd. behind Niagara Falls, is almost four times the size of the Bridge Street location, which staff said was in poor shape and didn’t have enough room to handle new fleet.

While an argument could have been made that the facts of the situation did not require the MOE be notified, staff and the consultant­s decided to err on the side of caution and notify the MOE.” City solicitor Ken Beaman

 ?? RAY SPITERI/NIAGARA FALLS REVIEW ?? Unexpected remedial action, and additional work as part of the demolition of the former Bridge Street transit building, has resulted in additional costs of $650,000.
RAY SPITERI/NIAGARA FALLS REVIEW Unexpected remedial action, and additional work as part of the demolition of the former Bridge Street transit building, has resulted in additional costs of $650,000.

Newspapers in English

Newspapers from Canada