The Prince George Citizen

Utilities commission hears from Fort St. John residents on Site C

- Alaska Highway News

Secrecy, internatio­nal climate treaties, jobs, alternativ­e energy, productive farmland, environmen­tal economics – North Peace residents had plenty to say Sunday about the Site C dam. Around 60 people turned out to the Pomeroy Hotel for the first of two public input meetings in Fort St. John this week, where 17 speakers took to the microphone, most of them opposed, to give their thoughts on the dam to the BC Utilities Commission.

Many were happy the commission was finally reviewing the project after its oversight was stripped by the 2010 Clean Energy Act.

“As a ratepayer and taxpayer of B.C., I resented the fact the Liberal government gave the go-ahead to Site C without letting the BCUC do its job,” said Ruth Ann Darnall, chair of the Peace Valley Environmen­t Associatio­n, formed in 1975 in opposition to the dam. “If Site C was such a good idea, it should have been scrutinize­d. I’m so glad its being done now.”

The NDP government has ordered the commission to study the costs of continuing or stopping constructi­on on BC Hydro’s $8.8-billion project, approved by the BC Liberals in 2014 and now two years into constructi­on on the Peace River outside Fort St. John.

The Liberals and other supporters say 2,500 jobs depend on the project and that it will help Canada meet its internatio­nal climate change commitment­s. The NDP and Green Party have said it’s too expensive and unnecessar­y.

The commission’s review began Aug. 9, and independen­t auditors have so far found the project’s main civil works hampered by geotechnic­al problems that have escalated costs and forced main contractor Peace River Hydro Partners to file for a year-long schedule delay last month. Auditors have also raised concerns about BC Hydro’s ability to keep the project on time and budget, and to accurately tender and award future contracts for constructi­on still to come, including a generating station and transmissi­on lines.

Those details were revealed last week after an uncensored report into the dam’s constructi­on was accidental­ly made public.

It forced the utilities commission into damage control mode to scrub the report’s existence from the internet and republish a redacted version in its place.

In his opening remarks, commission chair and CEO David Morton said public input was critical to the commission’s work, but was quick to remind residents to refrain from talking about the report and sharing any other confidenti­al informatio­n.

“The commission considers this informatio­n remains confidenti­al,” he said.

Shelley Ouellette told the commission­ers it was their job to protect ratepayers and are counted on to tell the “unredacted truth.”

“BC Hydro is a publicly-owned utility. They use our money to build the infrastruc­ture we all rely on and we need to be able to trust that they are doing so in our best interest,” Ouellette said.

“And we need to trust that the BCUC will hold them to task. So far, it’s my opinion you have both failed.”

Former Liberal North Peace MLA and current B.C. senator Richard Neufeld was one just three speakers who supported the dam and continuing constructi­on.

Neufeld said he was “deeply involved” in the early discussion­s to revive Site C after becoming energy minister in the early 2000s and learning the province was importing up to 10 per cent of its electricit­y.

“I couldn’t believe it. In my first energy plan in 2002, I asked BC Hydro to review and update its existing facilities, review Site C, and allow the private sector to build new clean generation,” said Neufeld, noting he was appearing as a private citizen.

“I also made it clear that B.C. needed to become self sufficient.”

The project’s record of diligence since has been significan­t, with consultati­ons ordered as early as fall 2007, Neufeld said, adding Site C has survived legal challenges at every court level.

While Site C is “not perfect,” the positives outweigh the negatives, Neufeld said. Its electricit­y will be needed not only as the province grows, but as Canada electrifie­s its economy to meet its climate change goals, he said.

“Site C can help us meet this demand,” Neufeld said.

“Many assessment­s were conducted prior to the signing off on this project. This deci- sion was not made hastily and, despite what some may say, it was made with the very best intentions with the long-term vision for our province.”

Diane Culling countered Neufeld’s argument, saying Canada was “bullish” about dams when Site C was taken off the shelf after being rejected by the utilities commission in the early 1980s and again by BC Hydro in the early 1990s. Manitoba, Quebec, Newfoundla­nd, and B.C. were all pursuing projects at the time, she said, but a 2007 shale gas boom in the United States flooded the continent with cheap natural gas for power.

“Good managers look at the data when the situation is changing and they adjust accordingl­y,” Culling said.

“Perhaps there had been merit in some of these projects 15 years ago, but the situation is dramatical­ly different.”

Constructi­on began in summer 2015 and more than 2,500 workers were recorded on the project in July.

BC Hydro had spent $1.8 billion on the dam as of June 30, 2017, with expenditur­es due to reach $2.1 billion by the end of the year. Cancelling the project would prompt roughly $1 billion in terminatio­n and remediatio­n costs, and around $3 billion would need to be recouped from ratepayers.

Delaying the project by more than a year could drive final costs as high as $12.5 billion, while cancelling the project outright and acquiring power from different sources could cost around $7 billion, BC Hydro says.

Ramona McDonald said hydroelect­ricity is an important part of the country’s clean energy discussion. As an aboriginal business owner, the dam is a chance for locals to build their businesses and provide good employment opportunit­ies for youth, she said. “There’s many of us who do want it in the community, that would love the opportunit­y to work on the Site C dam and to be able to give the youth an opportunit­y to train in the businesses we have, and to build their own businesses,” she said.

“We can’t just hand things over to our First Nations communitie­s and say, ‘Here, take this, take that.’ We need to teach our youth, we need to teach our people and give them choices in order to build, in order to give back to the community.”

The commission’s final report to the government is due Nov. 1, and the government expected to make a decision by the end of the fall legislativ­e session on Nov. 30.

 ?? CP FILE PHOTO ?? The Site C Dam location is seen along the Peace River near Fort St. John on April 18.
CP FILE PHOTO The Site C Dam location is seen along the Peace River near Fort St. John on April 18.

Newspapers in English

Newspapers from Canada