The Province

SITE C: Study says constructi­on pause would cost way more than cancelling or continuing

- Stephanie Ip sip@postmedia.com Twitter.com/stephanie_ip

It would cost more to pause constructi­on of Site C than it would to cancel it outright, according to a new study.

The independen­t report on the $8.8-billion hydroelect­ric dam was prepared by internatio­nal consulting firm Deloitte LLP and posted on the B.C. Utilities Commission’s website late Friday.

Deloitte aimed to answer key questions facing the utilities commission: Is Site C on schedule and on budget; what would it cost would be to pause the project; and what would it cost to cancel the project entirely.

The report is part of an NDP-ordered rethink of the B.C. Hydro mega-project that was a signature project of the previous Liberal government. The utilities commission will consider the Deloitte documents in compiling its preliminar­y report which is due Sept. 20.

According to Deloitte, the Peace River project is on time and on budget but is at risk of a significan­t delay and cost increases if it misses a river diversion scheduled for September 2019.

“If, however, the September 2019 start of river diversion milestone is not achieved and is delayed until September 2020, the project will likely experience the moderate-impact scenario,” Deloitte concluded.

The river needs to be diverted to allow constructi­on of the main dam and that work has to be done when water levels are low at the end of the summer.

Under the scenario of a one-year delay, Deloitte said, the cost of the project would jump by 10 to 20 per cent, leaving Site C at with a final price of between $9 billion and $10 billion.

If the project was set back by more than a year, Deloitte warned, Site C could end up with a final price as high as $12.5 billion.

The cost merely to suspend the project and preserve the work already done — to allow for constructi­on to resume in 2024 — would be $1.4 billion. But that figure does not include others costs that arise when constructi­on is re-started, nor does it take into account inflation.

The cost to cancel the project outright would be $1.2 billion, the report said, on top of the $4.5 billion already committed — which includes money already spent, the value of contracts already awarded and other costs. So if the project was cancelled, B.C. Hydro would be out $5.7 billion.

Site C is the largest constructi­on project in B.C.’s history. Approximat­ely 2,200 people continue to work at the site.

 ??  ??
 ?? — B.C. HYDRO ?? A report finds a one-year delay on Site C constructi­on could hike costs by 20 per cent.
— B.C. HYDRO A report finds a one-year delay on Site C constructi­on could hike costs by 20 per cent.

Newspapers in English

Newspapers from Canada