The Province

Commission wants more Site C answers

- DERRICK PENNER depenner@postmedia.com

Some of the biggest questions that need better answers in the B.C. Utilities Commission’s review of the $8.8-billion Site C dam are about power sources that could replace the mega-dam if it were cancelled, according to commission chairman David Morton.

After just six weeks of collecting submission­s from B.C. Hydro, the public and expert consultant Deloitte LLP, the commission released an interim report that detailed 73 questions it needs B.C. Hydro to answer before making recommenda­tions to government.

“Some of the missing pieces (are in) some of the sources that B.C. Hydro screened out,” said Morton. “We have some informatio­n from Deloitte, but we’d like to get Hydro’s take on the costs and viability of those.”

Site C would have the capacity to generate 1,100 megawatts of energy and supply some 5,300 gigawatt hours of electricit­y a year, enough to power 450,000 homes.

Morton said the commission panel needs to be able to factor in the cost of alternativ­es supplies into its analysis of the options, which include completing the project on schedule, suspending constructi­on with the option to restart later or cancelling it outright.

“It’s difficult to do the analysis,” Morton said. “It’s one thing to see if (the project) is on time on budget.”

However, if the project is terminated, with expected costs of $2.1 billion to wind up activity, remove the constructi­on camp and remediate the site, “then what do you do to replace the energy you’re not going to get from site C,” Morton said.

The Commission asked B.C. Hydro to submit more analysis of renewable-energy options that might substitute for Site C. The options the utility has include a collection of smaller wind farms, pumped-storage hydro projects, and with a sixth generating unit at its Revelstoke Dam.

And the Hydro analysis of its alternativ­es, which it estimated to be a more expensive option than Site C, did not account for forecasts of declining costs for wind and solar power installati­ons.

“We’ve asked B.C. Hydro to redo that modelling,” he said. That would let the Commission consider the affect on Hydro rates of opting for the alternativ­e power sources.

Alternativ­es to Site C have long been a point of discussion in B.C.’s energy sector. Critics have long argued B.C. Hydro’s forecasts for increasing demand did not consider things that would undercut the need for the dam.

In 2014, B.C.’s main lobby group for independen­t power producers, Clean Energy Associatio­n of B.C. made a last-ditch effort sell the provincial government on renewable-energy options that would be the equivalent of Site C’s output.

The associatio­n argued the roster of projects, which included wind farms, run-of-river generation and biomass plants, could be built in increments that wouldn’t leave B.C. Hydro with a big power surplus and be $1 billion cheaper.

At the time, then Clean Energy B.C. executive director Paul Kariya said it was an attempt to show its members could offer cost-competitiv­e alternativ­es to Site C, which is an important considerat­ion for the Commission review, according to Morton.

Newspapers in English

Newspapers from Canada