Saskatoon StarPhoenix

THE GREAT ROAD SHOW

A year after the Saskatchew­an government signed a $1.88-billion public-private partnershi­p contract for the Regina bypass, reporter Natascia Lypny got an opportunit­y to tour the province’s largest transporta­tion project.

- nlypny@postmedia.com

ON TIME, ON BUDGET

It’s an oft-cited comment with fixed-price and set-timeline projects, but project director Alisdair Dickinson said the project is on track. More than 120 staff and 500 labourers are toiling on the highway, which includes 12 overpasses, new and resurfaced highways, and new service roads.

Work is happening along the extent of the route, from Balgonie to Highway 11. Dickinson said “every day is a challenge in this industry,” but nothing has snagged the team yet. There have been no lost-time workplace incidents. David Stearns, Ministry of Highways and Infrastruc­ture executive director of major projects overseeing the bypass, said the build primarily aims to improve road safety, uninterrup­ted flow of traffic and access to the Global Transporta­tion Hub.

The consortium will be managing the bypass for 30 years after constructi­on completion.

HELLO DOWN THERE!

The team has dug five “borrow pits” like the one located east of the intersecti­on of the TransCanad­a Highway and Tower Road. The project is using 15 million cubic metres of material — largely dirt and sand — to build up embankment­s for the interchang­es and other areas.

To put that into perspectiv­e, the “big dig” of Wascana Lake was one million cubic metres. Equipment was trucked in from Fort McMurray, Alta., for this work, including 100-ton haul trucks that measure 15 feet high. Dickinson said the consortium is currently figuring out how the pits will be used post-constructi­on.

COMPLEX INTERCHANG­ES

This interchang­e at the TransCanad­a and Pinkie Road is the most complicate­d of the bunch. Like the one at Tower Road, it allows drivers to zip through the interchang­e without slowing down if they’re travelling east or west along the TransCanad­a. The work needed at Pinkie Road to mesh it with the bypass required the dismantlin­g of some of its relatively new components, but the team says most of the interchang­e is being salvaged. Although the west and south portions of the bypass are slated for completion in the fall of 2019, work is ongoing now.

EAST OF REGINA PRIORITIZE­D

Pushing for an October 2017 deadline, work is in full swing east of the city, like here at the Tower Road interchang­e. As with Pinkie Road, through-traffic will have an unimpeded route. Meanwhile, those heading into Regina will need to use a ramp and those exiting will take a bridge. The team has begun constructi­ng bridge structures for the interchang­es and is working on a north service road by Pilot Butte. That stretch, along with a new south service road, should be usable in the coming months. Dickinson said managing traffic while all this work is going on has been “fairly intensive” but there’s a light at the end of the highway.

 ??  ??
 ?? DON HEALY ?? Daniel Berube runs a Hitachi 1900 excavator at the Borrow Pit area of the Regina bypass project northwest of Regina. The Ministry of Highways and Infrastruc­ture and Regina Bypass Partners hosted a tour to allow media to see the work as it progresses.
DON HEALY Daniel Berube runs a Hitachi 1900 excavator at the Borrow Pit area of the Regina bypass project northwest of Regina. The Ministry of Highways and Infrastruc­ture and Regina Bypass Partners hosted a tour to allow media to see the work as it progresses.

Newspapers in English

Newspapers from Canada