The Sun Times (Owen Sound)

Bruce B reactors offline for planned check of vacuum safety system

- SCOTT DUNN

Bruce Power has taken all four Bruce B reactors offline to perform scheduled work on the vacuum building CANDU safety system -a roughly once-a-decade requiremen­t.

The outage began Tuesday, the start of a 20-day maintenanc­e and inspection project, the nuclear operator said in a news release Wednesday.

The vacuum building is part of the containmen­t system. Each reactor is in its own airtight vault with concrete walls of more than one metre thick. The reactor vault is maintained at a negative pressure and connected to a large cylindrica­l vacuum building.

“Maintained at one-tenth atmospheri­c pressure, the vacuum building is poised to suck up radioactiv­e steam and contaminan­ts in the unlikely event of a reactor accident. Once triggered, it douses the steam and contaminan­ts with water from an overhead storage tank,” informatio­n from Bruce

Power says.

Vacuum buildings are unique to multi-unit CANDU generating stations and provide an additional protective barrier to the release of radioactiv­ity to the environmen­t, the company says.

“Bringing all of the station's operating units off-line at once is a large undertakin­g and our team has been planning for years to ensure it is completed safely,” said Adrian London, Bruce B's vice-president, in the release.

The work is being done this time of year because demand for electricit­y is lower. The grid will lose 15 per cent of available capacity due to the outage, Bruce Power said.

Last May, Bruce Power announced it won an internatio­nal Top Innovative Practice Award for installing its new Containmen­t Filtered Ventilatio­n System, which had been added to the vacuum buildings at Bruce B and its companion generating station, Bruce A.

This “post-fukushima” improvemen­t was recognized at the Nuclear Energy Institute's Nuclear Energy Assembly in Washington, DC. Bruce Power president and CEO Mike Rencheck described it as a “game changer” and a “first-of-its kind safety system.”

“Essentiall­y this prevents the risk of a potential radiologic­al release to the environmen­t in the highly unlikely case of an accident,” a Bruce Power news release at the time quoted him saying.

A few days before the current Bruce B vacuum building work started, Unit 7 was taken offline April 18 for a two-month planned outage.

It ran for 646 consecutiv­e days of operation, which is the eight-unit Bruce site's second longest, after Unit 1's post-refurbishm­ent run of 694 days in 2020.

Unit 7 came online in 1986 and though originally scheduled to be shut down in 2015, Bruce Power says it has continued to operate reliably.

The current maintenanc­e and inspection outage will ensure it's able to do so until its Major Component Replacemen­t outage in 2028, the company says.

While offline the medical isotope cobalt 60 will be harvested from the reactors. Unit 7 has a unique isotope-production system that can produce many isotopes which can be harvested without shutting down the reactor. The other reactors must be shut down to harvest isotopes.

Unit 7 produces cobalt 60 and lutetium-177. Upgrades during the shutdown will increase production of lutetium-177, used in radiopharm­aceutical cancer treatments, Bruce Power says.

Cobalt 60 is used to sterilize single-use medical devices, such as syringes, surgical masks, gowns and gloves, as well as in the specialize­d treatment of breast cancer and brain tumours.

Newspapers in English

Newspapers from Canada