The Telegram (St. John's)

The latest testimony from the Muskrat Falls Inquiry

Former project team member Jason Kean stands by early number

- ashley.fitzpatric­k@thetelegra­m.com

The cost of the Muskrat Falls hydroelect­ric project has soared beyond the $6.2-billion estimate at sanction, but former deputy project manager Jason Kean says that’s not because the original, base estimate was faulty.

“I stand by the base estimate,” he said, during questionin­g at the Muskrat Falls Inquiry Thursday, having been grilled the day before about selective sharing of comments on his work.

“I felt 100 per cent confident in that number, based upon the conditions and constraint­s that were defined in the ‘Basis of Estimate,’” he said.

The “Basis of Estimate” is a detailed document of several hundred pages explaining how the project’s cost estimate was developed. It explains the base estimate includes: details on what will be built (exact scope of the project), how it will be done (including method of constructi­on and timeline requiremen­ts), expenses including materials and labour, and performanc­e factors such as productivi­ty.

The $6.2-billion figure was made up of (1) the base estimate, (2) an added amount for contingenc­y given some variations are likely to occur, and (3) an amount for price escalation (including things like inflation). The “contingenc­y” block also included an amount for “tactical risk” — for uncertaint­ies, like any unsettled definition on some sub-pieces of the build.

The $6.2-billion price tag did not include an amount to reflect “strategic risk” and a “management reserve” that could be establishe­d to cover. Testimony to date has referenced a report from Westney Consulting, apparently calling for $500 million to be at the ready for the project.

Lawyer Geoff Budden (the Muskrat Falls Concerned Citizens Coalition) was asking Kean about the estimated costs. He wanted to go further Thursday morning, to get Kean’s take on — beyond what has been said publicly — what might have caused the project’s cost to skyrocket during constructi­on. But Commission­er Richard Leblanc said that question was better suited to the second phase of the inquiry, coming in 2019.

At this point, the focus was placed on whether or not the early project estimates were on point and how risk was considered and handled.

Kean’s responses suggested many of the big answers there will have to come from various decision makers to testify later in the inquiry hearings, including former Nalcor Energy president and CEO Ed Martin, and the project lead at the time, Gilbert Bennett.

For example, asked about the use of a “P50” probabilit­y factor on estimates —50 per cent chance of overrun and 50 per cent chance of underrun — Kean made it clear his team would run the numbers, but didn’t make the decision on what to use. A higher “P” value, like a “P75,” would mean a higher cost estimate, but also less chance of a cost overrun.

On everything from determinin­g the cost of concrete to the number of transmissi­on towers needed for the Labrador-island Link, Kean defended the capabiliti­es of Snc-lavalin team members, including lead estimator Paul Lemay. He said that company’s team was responsibl­e for about 70 per cent of the base cost estimate.

“Mr. Lemay and the team he assembled were top notch,” he said.

He said he did support the decision to change the arrangemen­t with Snc-lavalin from an engineerin­g, procuremen­t and constructi­on management (EPCM) contractor to a joint “integrated management” team arrangemen­t. The Nalcor project team and Snc-lavalin weren’t on the same page on many fronts, for example on how work packages would be broken down for contractin­g.

He remained on the project until early 2017. In January 2017, he issued a one-month notice before his departure from the project. He told the inquiry he felt there was a value change, a change in ideology and messaging from the highest levels of the corporatio­n he didn’t agree with.

He has taken on work since as an independen­t consultant, including work for Westney Canada.

 ??  ?? Kean
Kean