Pennecon to complete Astaldi’s Muskrat Falls contract

- telegram@thetelegra­m.com

Pennecon Ltd. has been awarded a contract from Nalcor Energy to complete remaining work left by Astaldi Canada when it was ordered off the worksite in late-october.

“Pennecon, a Newfoundla­nd and Labrador company, is familiar with the Muskrat Falls Project and we are confident that their project experience will ensure this work is completed safely and effectivel­y,” read a statement from Nalcor CEO Stan Marshall on Thursday.

“The company understand­s Nalcor’s establishe­d hiring protocols which provide hiring preference­s for qualified members of Innu Nation first, followed by Labradoria­ns and then residents of the island.”

Nalcor has stated that Astaldi’s work is around 95 per cent complete. On Thursday, Nalcor reiterated a “commitment” to the existing cost and schedule of the project, saying further delays are not expected and the cost will not balloon beyond $12.7 billion.

Pennecon already has a number of contracts on the Muskrat Falls site. Most notably, Pennecon, in partnershi­p with United States-based Barnard constructi­on, has been working on the North and South dams on the project. The dams are expected to be completed by July, 2019.

Elsewhere, 129 non-unionized former Astaldi workers are likely to be without pay owed for work completed after Oct. 20.

Natural Resources Minister Siobhan Coady indicated on Wednesday that court proceeding­s between Astaldi and Nalcor remain on-going and will not conclude before Christmas.

 ?? FILE PHOTO ?? Pennecon Ltd. has been awarded the contract to finish work on the Muskrat Falls left incomplete by Astaldi Canada.