The Telegram (St. John's)

Muskrat Falls ready in year: Marshall

Nalcor CEO outlines tentative timeline for fully-commission­ed Muskrat Falls

- ANDREW ROBINSON THE TELEGRAM andrew.robinson @thetelegra­m.com @Cbnandrew

If all goes according to plan, Nalcor Energy CEO Stan Marshall can envision a fullycommi­ssioned Muskrat Falls one year from now.

Speaking at the provincial Crown energy corporatio­n’s annual meeting Tuesday, Marshall did caution there’s an elephant in the room that’s unpredicta­ble and already the cause of considerab­le delays to the multibilli­on-dollar project — the COVID-19 pandemic.

“The COVID-19 pandemic will persist for the remainder of the year and will probably continue into 2021,” Marshall said during the meeting, which usually takes place in April but was delayed and moved entirely online in light of the ongoing pandemic. “Any outlook is therefore clouded by the uncertaint­y and disruption this is causing.”

The hydroelect­ric project, now expected to exceed $13 billion in cost, does have an end in sight, with 99 per cent of the work completed. Equipment installati­on and commission­ing work resumed recently at the Muskrat Falls site after almost four months of inactivity, with Marshall noting this work is happening at a reduced level due to the pandemic.

Software issues have delayed the Labrador-island Link, but Marshall said interim software should be installed for trial operation within the next month. Also due to be ready before the end of the summer is a fullycommi­ssioned first generating unit to generate first power. The second unit of four in total would follow in the late fall.

All other elements of the project should be finished in the first half of 2021, leading to a fully-commission­ed site one year from now, Marshall said.

“For me, the last four years at Nalcor have been extremely challengin­g, and I am disappoint­ed that the Muskrat Falls project has not been completed in that timeframe,” said Marshall, who has hired in 2016 and earlier this year agreed to extend his stay as the CEO until the hydroelect­ric project is finished.

“However, the end is in sight, even through the fog of the COVID-19 pandemic. I am very proud of what we’ve been able to achieve at Nalcor over the past four years. None of this could have been possible without the continuing support of our dedicated employees and our board of directors, and I thank them all.”

One of those additional elements likely to go live in the first half of 2021 would be the third generating unit. Once that’s operationa­l, Nova Scotia-based Emera, owner of Nova Scotia Power, is due to receive 20 per cent of the power generated at Muskrat Falls. A 35-year Energy Access Agreement between Nalcor and Emera gives Nova Scotia ratepayers marketpric­e power and offers Nova Scotia Power a first look at excess power.

Earlier this year, the final report from the Muskrat Falls Inquiry was released, outlining a variety of poor decisions made to ensure the project proceeded, even if it failed to serve the best interests of Newfoundla­nd and Labrador residents. The provincial government first announced its intention to proceed with developing Muskrat Falls in 2010, with the initial cost estimate for the project below $7 billion.

“The recommenda­tions from these proceeding­s will need to be carefully considered by our management team and discussion­s held with our board of directors and our shareholde­rs,” Marshall said.

In the financial updates announced Tuesday, Nalcor reported a year-end profit of $126 million for 2019, down $54 million from the $180 million profit reported for 2018. For the first quarter of 2020, the corporatio­n recorded a loss of $171 million, a $263 million decrease from the $92 million profit recorded for the same time period last year.

 ?? CONTRIBUTE­D ?? An aerial view of the Muskrat Falls site.
CONTRIBUTE­D An aerial view of the Muskrat Falls site.
 ??  ?? Marshall
Marshall

Newspapers in English

Newspapers from Canada