The Telegram (St. John's)

MP wants to know why roadwork is behind schedule

Yvonne Jones says it happens every year

- EVAN CAREEN LOCAL JOURNALISM INITIATIVE REPORTER  telegram @thetelegra­m.com  @Stjohnstel­egram

Labrador MP Yvonne Jones wants to know why some paving projects in Labrador are behind schedule and what the province is doing about it. Jones took to social media recently with questions about paving on Route 510, the Trans-labrador Highway (TLH), and why the tendered project hasn’t started yet this year.

“We are last to see any work starting on the highway,” she said.

“It’s not the first year, it’s a continuing issue, year over year. People in Labrador are just fed up. If this were any other highway, it would be completed right now. It’s taking forever to do it.”

According to the Department of Transporta­tion and Works, the company that has the contract, Johnson’s Constructi­on out of Corner

Brook, has until the end of this paving season to complete the 80 kilometres between Happy Valley-goose Bay and Cartwright Junction and prepared the roadbed last year.

“Road work that started in 2019 has resumed this year, such as crushing of granular and placing class A granular, which is necessary to take place before paving,” a statement from the department read. “The company has met the obligation­s of the contract and is preparing to complete paving on this contract this constructi­on season.”

Jones said, as a representa­tive of the federal government, she wants to know why the roadwork hasn’t begun.

Roadwork costs on the TLH are cost shared between the provincial and federal government­s. Jones said as a representa­tive of the federal government she wants to know why the roadwork this summer hasn’t begun yet.

“Some of this money has been approved federally for about three years now,” she said. “We’ve been approving money for this section of highway and cost share it. When those tenders go out you expect those companies to be there to start the work and that’s not occurring.”

Jones said she was told by the company the equipment needed for the paving was moved from Labrador to the island and would be sent back to Labrador soon.

If they can’t meet the requiremen­ts for completing the contract on time, she wants penalties imposed.

“It was here, it was in Labrador and for some reason in June they moved it out,” she said. “By the time it gets back here that gives us about five weeks paving. We’re lucky if we get 30-40 km paved this year.” Jones said there are penalties that can be imposed for a company not completing a contract on time and she wants to know if those are enforced and if they will be if the company can’t complete the 80 km this year.

Transporta­tion and Works said there are clauses in many road work contracts regarding “liquidated damages” if contractor­s do not meet the requiremen­ts of the contract.

“However, Johnson has submitted a schedule that indicates paving on the twoyear contract awarded last year will be completed this year,” the statement read.

They also awarded the company a tender for 2020 to pave 127 km of the TLH, which Transporta­tion and Works says they have until 2022 to complete.

Saltwire Network contacted Johnson’s Constructi­on regarding the road work, but a reply was not received by publicatio­n deadline.

 ??  ?? Jones
Jones

Newspapers in English

Newspapers from Canada