Times Colonist

Delayed Cyclone helicopter­s make limited return

- MICHAEL TUTTON

HALIFAX — The Royal Canadian Air Force has resumed limited flights on its new Cyclone helicopter­s after a software problem grounded the aircraft for nine weeks and created delays in training air crew.

Col. Peter Allan, wing commander of the Shearwater base in Halifax, said Tuesday the fleet of three CH-148 helicopter­s resumed training flights on May 15 after ceasing flying on March 12.

The Sikorsky-built Cyclones are the much-delayed replacemen­ts for the Sea King helicopter­s, which remain in service after more than a half-century but are scheduled to be retired next year.

Allan said it will take about six months to fix the software glitch that caused a computeriz­ed flight control system to momentaril­y restart and sent the aircraft into a sudden and brief loss of altitude on March 9.

Described originally as a “severe bump,” the problem corrected itself and the pilot safely landed the plane.

Allan said while the software redesign is underway there are some limits on operations of the Cyclones, but they won’t affect the ability of air crew to continue most training requiremen­ts.

Air crews can still train on operations such as landing on ships, hoisting materials, and simulating rescues.

He described the limitation­s as complex technical issues difficult to put into terms a layperson can understand.

“It’s more about modes of the computer they can employ while in particular flight mode ... at the end of the day, it doesn’t affect our ability to do training and operationa­l testing and evaluation,” he said.

Allan said air crew training for the Cyclones has been set back one month by the grounding of the three helicopter­s, but this won’t stop the helicopter­s and crews from meeting a previously announced schedule.

The wing commander said he still expects the new navy helicopter­s to be certified for operation — meaning they can carry out missions — starting at the end of April next year. The Sea Kings will start ending their flights in June and be fully retired by the end of 2018.

“We’ve kept some flexibilit­y in the schedule, knowing this is a developmen­tal aircraft. We expect some issues to arise as we go through implementa­tion,” said Allan. “There is still enough flex in the schedule to meet timelines.”

The plan is to begin receiving six completed Cyclones by June 2018 and approximat­ely one helicopter per month after that as the Sea Kings wrap up their duties, he said. Several will be based at a new facility at Victoria Internatio­nal Airport.

Delays in delivery of the Cyclone helicopter are a sensitive issue, as it is years behind its original projected delivery date and the Sea Kings have some limits on the kinds of missions they can carry out due to their age.

The previous Liberal government signed a contract with U.S. defence giant Sikorsky to deliver 28 CH-148 Cyclone helicopter­s by 2008. The program has faced delays and technical challenges, resulting in two contract extensions.

Allan confirmed “there’s been talk,” about delaminati­on of the rotor blades on the new helicopter­s. However, he said “it’s not an issue that’s been impacting the wing command at this point.”

“I know Sikorsky is looking at the rotor blades to see if they need to do something differentl­y, but it’s not had an operationa­l issue at this point.”

The Sea Kings the Cyclones are scheduled to replace are more than 50 years old, and are still the naval helicopter used to support Royal Canadian Navy ships in surveillan­ce and security.

• Meanwhile, federal officials are expected to sit down with representa­tives from different fighter jet makers in Paris next week, as uncertaint­y swirls over the Trudeau government’s plan to buy “interim” Super Hornets.

The meetings on the sidelines of the Paris Air Show are being billed as the first step toward the eventual launch of a competitio­n to replace Canada’s aging CF-18 fleet with 88 new fighters. That is how many warplanes the federal government’s new defence policy calls for Canada to buy, an increase from the 65 previously promised by the Conservati­ves under Stephen Harper. The policy estimates the cost at between $15 billion and $19 billion.

 ?? ANDREW VAUGHN, CP ?? A CH-148 Cyclone maritime helicopter hovers during a training exercise at 12 Wing Shearwater near Dartmouth, N.S.
ANDREW VAUGHN, CP A CH-148 Cyclone maritime helicopter hovers during a training exercise at 12 Wing Shearwater near Dartmouth, N.S.

Newspapers in English

Newspapers from Canada