With these giant rings, Victoria will be wedded to bridge shape

300-ton pieces for the new Johnson Street span are expected to be lifted into place next month

- BILL CLEVERLEY

The 300-ton rings that will define the look of new Johnson Street Bridge should be lifted into place in late November.

The exact timing is dependent on the availabili­ty of a massive crane known as the Dynamic Beast that is capable of lifting the pieces — including the rings and a counterwei­ght — into place, project director Jonathan Huggett told councillor­s.

“We will be in a position to start lifting and assembling the rings in the structure on Nov. 10,” Huggett said during his quarterly progress report.

The Dynamic Beast, anchored off the Lower Mainland, sits on a barge measuring 330 feet by 120 feet and is capable of lifting 900 tons.

Huggett said the marine channel will be blocked for two days for the operation, but traffic over the existing bridge will face only intermitte­nt interrupti­ons of, it is hoped, no more than an hour at a time.

Traffic will not be allowed on the bridge while the rings are being lifted, he said.

“Because you plan for the worst and you hope for the best. Obviously, we don’t want 300-ton rings swinging around in the breeze with anybody in traffic on that bridge,” Huggett said.

“So while it’s in the air, the traffic on that bridge will be shut down.”

The first shipment of steel, which included the north and south rings, the lower counterwei­ght and the temporary structure used to support the components of the bridge as they’re pieced together, arrived in Victoria from China in late August and was offloaded at Port Hope Shipyard.

Crews have been at work prepping the rings for installati­on — completing the painting and mounting, aligning and installing support structures.

Installati­on of the bridge span support segments is meticulous, precise work, Huggett said.

The completed main bascule leaf, including walkways and cycling paths, will be lifted in a single operation and bolted to the rings in January.

Commission­ing and testing of the bridge will be done in February and March, with the opening scheduled for March 31, Huggett said

The bridge’s cost was estimated at $63 million in 2009 and grew to $92.8 million when the contract to build it was awarded to PCL Constructo­rs Westcoast in 2012. Constructi­on began in May 2013, and the price is now up to $105 million.