Times Colonist

Site C cost could top $10 billion: report

Review should be viewed as supporting alternativ­e energy industry, Weaver says

- DIRK MEISSNER

The B.C. government says it will decide the future of the Site C hydroelect­ric dam by the end of the year after an independen­t review concluded the $8.3<billion megaprojec­t is over budget and behind schedule.

The British Columbia Utilities Commission says the dam is not likely to be completed by a 2024 deadline and could end up costing 20 to 50 per cent more than budgeted, increasing completion costs to above $10 billion.

The minority NDP government asked the utilities regulator to examine the project’s economic viability, which was a signature job-creation initiative of former Liberal premier Christy Clark.

Energy Minister Michelle Mungall said cabinet must decide by the end of this year whether to cancel the project or continue constructi­on, which started more than two years ago.

“We will be going forward, reviewing this in detail,” she said. “We will be consulting with First Nations and we will be delivering our decision to British Columbians by the end of this year. This is a very serious decision. It’s going to be impacting the future of our province.”

Mungall said the project’s costs will drive the government’s decision and it is aware the jobs of more than 2,000 people are at stake.

“We appreciate that this is tough on everyone,” Mungall said.

The commission was asked to confirm whether Crown-owned B.C. Hydro is on target to complete Site C on budget and by 2024. It was also asked to provide advice on three possible outcomes: proceeding with the project, suspending constructi­on until 2024 or terminatin­g it.

The commission concluded suspending and restarting the project in 2024 is the least attractive option, adding at least $3.6 billion to its final costs.

Mungall agreed suspending constructi­on is not a viable option, which leaves the government to decide between going ahead or stopping constructi­on.

The review doesn’t make a recommenda­tion on whether the province should proceed or cancel the dam, but it said terminatin­g the project would cost $1.8 billion while completing it could cost more than $10 billion.

The commission said there are viable alternativ­e energy sources including wind, geothermal and industrial curtailmen­t that could provide similar benefits to Site C with an equal or lower cost.

Commission chairman David Morton said B.C. Hydro produced a low-risk scenario before the start of constructi­on that estimated Site C would cost more than $10 billion, but chose to focus on its higher risk total cost projection of $8.3 billion, plus contingenc­y costs.

He said the commission has provided the government with a detailed analysis of the economics of Site C. “There’s a lot of cost to ratepayer and economic informatio­n in this report and we’re hopeful it’s enough informatio­n of that nature,” Morton said.

Liberal Mike Bernier, who represents northeast communitie­s near the dam site, said thousands of jobs are at stake and the government is considerin­g writing off the estimated $4 billion already spent on Site C. “Site C is one of these projects that is going to make sure for generation­s to come we have cheap, reliable, clean, firm power,” he said.

But environmen­tal groups and activists said the review confirms there are cost-effective and environmen­tally friendly alternativ­es to building a dam that will flood agricultur­al land and create an 83-kilometre long reservoir.

“Their analysis is pretty damning,” said Harry Swain, the former chairman of a federal-provincial joint review panel that issued a report in 2014 that the province used to proceed with Site C.

“The summary would be, if they were allowed to make a recommenda­tion: ‘Gosh, don’t do this.’ ”

Green Leader Andrew Weaver said the Liberals recklessly viewed Site C as an energy source for their failed attempts to bring a liquefied natural gas industry to B.C.

He said the utilities commission review should be viewed as a statement in support of the alternativ­e energy industry.

B.C. Hydro’s 866-page submission to the commission said completing the dam as planned would still be best for ratepayers and terminatin­g the project would cost $7.3 billion on a present-value basis.

The submission said demand for electricit­y is growing and without the dam, the province would hit an energy shortfall by 2031.

Site C would be the third dam on the Peace River, near Fort St. John.

Newspapers in English

Newspapers from Canada