Times Colonist

Who’s minding Site C project?

- DERMOD TRAVIS

Lost in the threats and counter-threats over the Trans Mountain pipeline is news that B.C. Hydro will be cutting a cheque to Flatiron/Graham, principal contractor­s on the Lower Mainland Transmissi­on Line for about $100 million, following a semi-successful arbitratio­n, depending upon your perspectiv­e.

Announced in 2009, the then-$602 million line was to be completed by 2014. It came in “on budget and on time” in 2015, at a cost of $743 million or — in the words of thenpresid­ent and CEO Jessica McDonald — “about $18 million higher than Hydro’s original budget of $725 million.”

The line was riddled with errors from the get-go: failure to consult with First Nations, substandar­d steel imported from India and frustratio­ns that led the utility to complete one section of the line itself.

In 2015, reacting to the growing litany of problems plaguing the line, former energy minister Bill Bennett cut to the chase: “Hydro has characteri­zed [the problem] as a failure to perform.”

The utility was more nuanced a few months later, stating: “The contractor faced scheduling pressures during constructi­on and, based on feedback from the contractor, B.C. Hydro pushed the in-service date to late 2015.” The current cost for the line now stands at $828 million. Flatiron has also run into “scheduling pressures” in Montreal, along with SNC-Lavalin, ACS Grupo, Hochtief, Dragados Canada and EBC Inc., all members of the consortium building that city’s new Champlain bridge.

Pressures that an additional $235 million from the federal government somehow managed to fix. Flatiron is getting another kick at the can on Site C. In March, the utility announced that it had awarded AFDE Partnershi­p a $1.6-billion contract for “the generating station and spillways civil works component” of the project.”

AFDE is made up of Aecon, Flatiron, Dragados and EBC Inc.

Constructi­on highlights of the contract include “installati­on of 34,000 tonnes of rebar.”

Rebar can be tricky, as the Windsor Essex Mobility Group consortium learned in 2013, when it had to replace “500 pre-stressed concrete bridge girders due to the use of tack welding” on the Detroit River Internatio­nal Crossing project.

Scheduling pressures, too, as the Windsor Star reported in March 2015.

WEMG had bid $200 million less than the Ontario government’s estimate for the project, and likely won the contract as a result of that bid and its promise to meet the targeted opening at the end of 2014.

It didn’t. The penalty of $100,000 a day ran into the the “millions of dollars.” WEMG is a partnershi­p between Fluor Canada Ltd., Acciona Concession­s and ACS (Dragados’ parent company).

Despite working alongside them on the Windsor project, Acciona is actually a competitor of ACS and has its own Site C contract, which hasn’t worked out so well.

In 2015, Hydro awarded the main civil-works contract to Peace River Hydro Partners, which was then made up of Acciona, Petrowest Corp. and Samsung C&T Ltd. It was the lowest bid at $1.75 billion.

In its report for the B.C. Utilities Commission, Deloitte LLP felt that PRHP’s “ability to meet critical milestones poses a major risk to the project.”

It noted that PRHP “may have significan­tly underbid the project, by $285 million to $345 million.”

Fellow PRHP member Samsung C&T “was widely believed to have underbid” for work on an Australian ironore project, Roy Hill Mine, in 2013. In 2016, the company reported a $1-billion loss on the project. Petrowest filed for bankruptcy in August 2017. After Deloitte submitted its report, news broke that the project had missed a key deadline and the river diversion would be delayed by one year, at a cost of $610 million, a sum not included in the Deloitte report.

Scheduling pressures come with an additional price tag: Every month of delay will result in an additional $21 million in interest costs.

The government won’t get much flak from one group of power brokers, though. Of the $1.25 million unions donated to the B.C. NDP between July 18 and Dec. 31, 2017, $860,000 of it came from vocal supporters of the government’s decision to proceed with Site C.

We’ll see how their members react in a few years to their utility bills, because the chances that Site C will come in at $10.7 billion are about the same as pigs flying.

Dermod Travis is the executive director of IntegrityB­C.

 ??  ??

Newspapers in English

Newspapers from Canada