NEB approves modified Burnaby terminal plans for pipeline

-

CALGARY — The National Energy Board said it has approved modified plans for the Burnaby Terminal of the Trans Mountain pipeline project, clearing a final regulatory hurdle for constructi­on to start.

The regulator said the approved variance applicatio­n will significan­tly improve safety at the terminal, which is the end point for the controvers­ial pipeline the federal government has agreed to buy as part of a $4.5-billion acquisitio­n of Kinder Morgan Canada’s core assets.

The new plans reduce the diameter of five of the 14 tanks and the overall capacity of the facilities by about 320,000 barrels, increase the space between the tanks, and reconfigur­e the secondary containmen­t system at the tank farm to reduce fire risk.

The NEB said its approval of the variance and Kinder Morgan Canada’s fulfillmen­t of certain conditions allows it to begin constructi­on at the Burnaby Terminal, subject to any other permits or authorizat­ions which may be required.

Burnaby, in a submission to the NEB, said the company failed to consult with the city, and that the modified plans don’t address its significan­t concerns on boil-over, vapour cloud explosion, and other risks.

The Burnaby site has been a focal point of opposition to the project as protesters raise concerns about potential spill damage.