Times Colonist

Alberta to build power storage unit near infamous mine

- DAN HEALING

CALGARY — A hydro power storage project proposed at the site of one of the worst coal mining environmen­tal disasters in Canada has been given regulatory approval.

Turning Point Generation, developer of the Canyon Creek Pumped Hydro Energy Storage Project, says the recent ruling by the Alberta Utilities Commission means it can now seek financial support for what it says would be the first large-scale energy storage project in the province.

Canyon Creek is to be located next to the decommissi­oned Obed Mountain open pit thermal coal mine 60 kilometres east of Jasper National Park, said Kipp Horton, CEO of Calgary-based WindRiver Power Corp., the parent company of Turning Point.

“We’re repurposin­g the site for what we believe is a modern grid type of product,” he said, pointing out the project will be able to utilize mine roads and a high-voltage power connection to reduce new environmen­tal disturbanc­es.

In November 2013, one of the then-suspended mine’s tailings dams failed, releasing an estimated 670 million litres of slurry into two creeks that fed into the Athabasca River, thus sending fine rock, clay and unrecovere­d coal particles as far as Lake Athabasca, 500 kilometres away.

The mine owner was handed nearly $4.5 million in federal and provincial penalties in 2017.

The Canyon Creek facility will consist of two new 40-hectare water storage ponds, connected by a five-kilometre, two-to-threemetre-wide pipeline, Horton said.

At night, when power demand is low, water will be pumped from the lower to the upper pond, gaining 500 metres of elevation. When demand is high, the water will flow the other way, turning a turbine generator producing 75 megawatts, enough to power about 50,000 homes, for up to 37 hours at a time.

“Typically, the price of power goes down during the night because we’re all sleeping, industry isn’t using it and, in Alberta, in fact, the wind blows stronger at night,” said Horton.

“We can be a sponge and soak up that power that’s being produced at night .. run our pumps, move that water uphill 500 metres in elevation and then have a fully charged battery, in a sense, ready for 8 a.m. when Alberta wakes up and starts flicking on lights.”

The only other pumped hydro system in Canada has been in use at Niagara Falls in Ontario since the 1950s, he said.

Calgary-based TransAlta Corp. has proposed adding a pumped hydro component to more than double capacity at its existing 355-MW Brazeau facility on the North Saskatchew­an River southwest of Edmonton.

It has set a 2021 target to start constructi­on, subject to winning a long-term contract.

Horton said he is also looking for customers to sign long-term contracts, but hopes to start constructi­on on the much smaller Canyon Creek project by next spring and have it operationa­l by the end of 2020.

He said the capital cost will be in the millions but has yet to be finalized.

In its decision, the regulator found that the project “is in the public interest” in terms of social, economic and environmen­tal effects.

In February, Alberta’s NDP government unveiled its second request for proposals to build renewable power projects, targeting a total of 700 MW of new capacity, with 300 MW reserved for proposals with Indigenous equity ownership.

Newspapers in English

Newspapers from Canada