Times Colonist

Amid controvers­y, Trans Mountain continues with expansion project

- DERRICK PENNER

Constructi­on crews remain busy driving piles for new facilities at Trans Mountain’s Westridge marine terminal on Burrard Inlet and clearing land at the Burnaby Mountain terminus of its pipeline, but industry leaders remain apprehensi­ve about the expansion project.

“Everyone is guarded about what does this mean,” said Chris Gardner, president of the Independen­t Contractor­s and Business Associatio­n about last week’s announceme­nt that constructi­on on the $7.4 billion project had officially restarted.

“Are we stopping and starting and stopping and starting,” Gardner said. “There has been so much uncertaint­y, there is definitely a degree of skepticism about some of these announceme­nts and activity we see.”

Last Tuesday’s announceme­nt near Edmonton by Trans Mountain CEO Ian Anderson, accompanie­d by new Natural Resources Minister Seamus O’Reagan and Alberta Energy Minister Sonya Savage, marked the restart of putting new pipe in the ground for the twinned pipeline.

That touched off what Anderson said would be a 22-month timeline to have the twinned facility, nearly tripling its capacity to 890,000 barrels of oil per day, in service by late 2022, although the overall project is not any less contentiou­s among its opponents.

However, in Burnaby, about 100 trucks per day are moving in and out of Trans Mountain’s terminal site, said project spokeswoma­n Ali Hounsell, as crews continue with clearing and stripping ground for expansion of its tank facilities and new water treatment system.

“It’s a busy, busy constructi­on site,” Hounsell said. “Things are happening,” and have been happening since August following the federal government’s re-approval of the project in June.

At last count, Hounsell said Trans Mountain and its prime contractor­s have hired 2,200 workers for the project.

At Trans Mountain’s Westridge Marine terminal, Hounsell said two barges are on site and have driven 25 of the 160 piles that will support expansion of the foreshore facilities for three new docks for loading ships.

“We’re also working through the regulatory process, particular­ly on the land side,” Hounsell said.

The project’s initial federal approval in 2018 was scrapped by the Federal Court of Appeal over inadequate consultati­on with First Nations, delaying constructi­on by about a year.

Hounsell said that with a new approval in June, Trans Mountain has had to re-file plans for all landowners also to be re-approved and deal with any outstandin­g complaints.

As far as putting new pipe in the ground is concerned, while Anderson promised that would begin “before Christmas,” it will be later into 2020 before that work starts in earnest in B.C.

The actual pipeline constructi­on has been broken up into seven separate segments, referred to as spreads in industry jargon. The first two of those are in Alberta, the rest are in B.C. with Spread 7, the final section, running through the Lower Mainland.

Gardner said the contractor on that section, the Kiewit Ledcor Trans Mountain Expansion Partnershi­p, hasn’t mobilized a workforce for the work yet.

“We want to see the pipeline built and hopefully now it will go ahead,” Gardner said, “but we’re not seeing that much on-the-ground activity in British Columbia.”

Gardner said there has been enough uncertaint­y over the project, “there is a degree of skepticism about some of these announceme­nts and activities.”

The Federal Court of Appeal, in a decision in September, ruled that six First Nations could file new legal challenges of the Trans Mountain project on the question of whether the federal government has fulfilled its obligation to consult with First Nations.

Judy Wilson, secretary treasurer for the Union of B.C. Indian Chiefs and Chief of the Neskonlith First Nation in B.C.’s Interior, said she will “continue doing what we need to do” to uphold the collective rights of First Nations people.

Trans Mountain has signed 57 impact benefit agreements with First Nations along the pipeline’s route, but Wilson said those agreements should only be in effect on federal First Nations reserve lands, not territoria­l lands outside of reserves.

Wilson argued that Aboriginal title to territoria­l land still rests with the First Nations families associated with those areas, not Band Councils, and government hasn’t received their consent, under the principles of the United Nations Declaratio­n on the Rights of Indigenous Peoples.

As well, cities such as Vancouver, Burnaby and Victoria remain opposed to the project, so “it is a wider issue.”

“They can do all the photo ops they want, but there are substantiv­e issues that haven’t been dealt with,” Wilson said.

Hounsel said the agreements that Trans Mountain has with First Nations are for the project’s right of way and “demonstrat­e the breadth” of support for it. She added that the agreements aren’t closed, the company is in continuing discussion­s with First Nations.

“We’ll continue to build with the appropriat­e permits and approvals in place,” Hounsel said. “If there are challenges, it doesn’t negate the approvals we have until such time as they are upheld in court.”

 ??  ?? Workers survey around pipe to start right-of-way constructi­on for the Trans Mountain Expansion Project, in Acheson, Alta. The 22-month timeline will have the twinned facility to Burnaby nearly triple capacity to 890,000 barrels of oil per day, in service by late 2022.
Workers survey around pipe to start right-of-way constructi­on for the Trans Mountain Expansion Project, in Acheson, Alta. The 22-month timeline will have the twinned facility to Burnaby nearly triple capacity to 890,000 barrels of oil per day, in service by late 2022.

Newspapers in English

Newspapers from Canada