Advice on SRT safety kept secret by TTC

- JENNIFER PAGLIARO CITY HALL BUREAU

The TTC hired consultant­s to provide expert advice on safely operating the Scarboroug­h RT beyond its expected life until a planned subway extension can be opened.

But that advice, and the outlook on the SRT’s life expectancy, are being kept secret from the public.

TTC spokespers­on Brad Ross says the transit agency signed a nondisclos­ure agreement that prevents it from publishing reports referenced in an update to the TTC board to be discussed May 8.

That board report recommends increasing the contract amount by $5.3 million to complete “urgently required” repairs to the entire fleet of trains. The trains’ undercarri­age wheel assemblies, the report notes, are already past their “design life,” but the trains are expected to stay in operation until at least 2026 when a one-stop subway extension is expected to be finished.

TTC continued on GT8

That contentiou­s $3.35-billion extension has yet to be approved by council for constructi­on.

Without the SRT operating during the constructi­on period, commuters would be left to take buses.

In 2017, the TTC reported it had discovered corrosion issues with the SRT trains that could cause “catastroph­ic” structural failures if not addressed.

Bombardier Transporta­tion, which now owns the SRT technology, was hired to provide “expert advice of how to safely operate the SRT past end of life,” the new board report says. The company is testing for “hidden cracks on key structural components” and coming up with a plan to keep the train cars in service.

WSP Canada Inc. was hired to “provide oversight” of that work. A second consultant, CH2MH, was hired “to review Bombardier Transporta­tion’s original analysis, findings and recommenda­tions.”

When the Star asked to review work from Bombardier and the two consultant­s, which was not included with the publicly posted board report, Ross said it could not be provided because the TTC signed a nondisclos­ure agreement.

When asked why the public agency would agree to keep work concerning the safe operation of a transit line confidenti­al, Ross said it agreed in order to release design data to third parties for review.

“The work contained in the reports was provided to the TTC by the vendors with (a nondisclos­ure agreement) as it contains valuable informatio­n usable by other owners of similar vehicles,” Ross said in an email.

Bombardier purchased the SRT’s technology — which differs from that of a subway or LRT — from the original manufactur­er, the provincial­ly owned Urban Transporta­tion Developmen­t Corporatio­n, in the 1990s, according to Bombardier’s website.

The SRT opened in 1985 with technology that is now considered outdated.

Releasing the reports, Ross said, would have a “negative impact” for Bombardier.

When asked specifical­ly if the SRT trains will be safe to operate until 2026, Ross said: “Bombardier provided a plan on how to achieve continued operations to 2026.”

Ross said the consultant­s concluded “that the work being done meets the recommende­d requiremen­ts to extend the life” of the SRT parts.

The repair money is budgeted as part of the Scarboroug­h sub- way extension, which is being funded with $910 million to be collected from a special tax on all Toronto homeowners for at least 30 years. To date, $14 million of $68 million budgeted through 2022 for vehicle repairs has been allocated, Ross said.

In 2013, council scrapped plans to replace the SRT with a seven-stop LRT in the same corridor. That LRT would have been fully funded by the province and, as previously planned, would have been operationa­l in 2019. The province also would have been responsibl­e for SRT life extension costs and bus replacemen­t during constructi­on.