Toronto Star

Uxbridge culvert project stalls

$17-million replacemen­t expected to reduce flood risks on Brock St.

- MOYA DILLON

Shovels are in the ground, but delays have plagued the completion of the long-awaited Brock St. culvert replacemen­t.

The $17-million culvert will be the largest infrastruc­ture project in the township’s history. It will reduce flood risk in the downtown area while lifting much of the area out of the flood plain.

“It’s the largest constructi­on project we’ve ever done, and it will allow our downtown to be developed by pulling us out of the flood plain,” Mayor Dave Barton said.

“Redevelopm­ent possibilit­ies could include commercial, residentia­l and retail. This will create opportunit­ies that will guide us for the next 50 years.”

Ground was officially broken on the project in September, although work was stalled in November after land acquisitio­n negotiatio­ns fell through for a parcel of land.

Although council can’t speak to the legalities of the matter, Barton said he expects some action early in the new year.

“At the moment, we do not have the access we require to complete the culvert,” he explained. “Council is aligned and have given clear direction on how to move forward, but it’s a process. Early in the new year there will be action on this file to secure the land so we can continue with this constructi­on project.”

Land acquisitio­ns aren’t the only issues plaguing the project.

When the project was originally funded in 2015, through a four-way partnershi­p with the township and regional, federal and provincial government­s, each party pledged to contribute $2.5 million to cover the then $10-million constructi­on estimate. Since then, constructi­on costs have increased to $12 million and ancillary costs, such as land acquisitio­n, environmen­tal studies and more, tallied up to another $5 million.

“I’m extremely frustrated that we’re in this position,” Barton said of the stalled land negotiatio­ns and other issues.

“This new council has walked into a very complex and difficult situation. We’re completely aligned to move forward and get this completed, but it will take some time. I’m extremely frustrated that we’re in this position where we’ve issued a contract for the project and not secured the land, but we’re remedying that as quickly as we possibly can.”

Once the land is secured, Barton said, some constructi­on work can begin immediatel­y, although the bulk of the work would likely restart in the spring.

“Things like tearing down the building that needs to come down and preparing the site for constructi­on can begin as soon as possible,” he said.

“But the major, invasive constructi­on would begin in the spring.”

Despite the headaches, the project remains a critical one for the future of the township.

“If we didn’t do this project — that’s not an option. It’s in very, very poor shape. It’s not a question of if it will fail, but when it will fail,” Barton said of the existing culvert.

 ?? RYAN PFEIFFER METROLAND FILE PHOTO ?? The project is expected to take about a year, but has hit delays that could push work into spring.
RYAN PFEIFFER METROLAND FILE PHOTO The project is expected to take about a year, but has hit delays that could push work into spring.

Newspapers in English

Newspapers from Canada