TTC faces growing maintenanc­e backlog for new streetcars

Work orders have nearly doubled since February, when number was deemed ‘unacceptab­le’

- BEN SPURR TRANSPORTA­TION REPORTER

The amount of maintenanc­e required on the city’s new streetcar fleet has ballooned — to nearly double the amount that was deemed “unacceptab­le” in internal TTC emails in February — as the vehicles continue to fall below reliabilit­y targets.

At the same time, TTC documents show the agency isn’t using a clause in the contract that allows it to withhold a portion of payment for defects.

However, the transit agency and the cars’ manufactur­er say there’s no cause for concern.

According to statistics provided by the TTC, earlier this month the number of open work orders — pending maintenanc­e, repair or modificati­on jobs — for the Bombardier-made streetcars had grown to roughly 11,000, up from 6,000 in February.

That coincides with an increase in vehicles approved for service, to165 streetcars from 120.

As the Star has previously reported, in February the TTC’s chief vehicle officer privately warned colleagues that having 6,000 open work orders was “unacceptab­le” and the volume of maintenanc­e risked becoming “unmanageab­le — if it is not already so.”

Although the amount of work the cars require has only grown since then, TTC spokespers­on Stuart Green said that doesn’t indicate a problem with the vehicles.

Green asserted that in addition to any work needed to fix problems with the cars, the work orders include routine maintenanc­e tasks such as replacing parts that have worn out, and exterior and interior cleaning.

“The number of open work orders is not a reflection of contract or vehicle performanc­e,” Green said in an email. Bombardier spokespers­on Kaven Delarosbil also said in an email the number of work orders “cannot and should not be interprete­d as a reflection of the performanc­e of the vehicle; more cars in service means more maintenanc­e activity overtime, simple math.”

Delarosbil said Bombardier “is working hand in hand with its suppliers and TTC to identify and implement technical solutions and improve overall reliabilit­y,” but the number of work orders “is not a concern.”

TTC work orders can describe a wide range of jobs, from important repairs such as correcting brake failures and replacing defective parts, to minor cosmetic fixes such as rectifying bad paint jobs or removing graffiti.

They can also include modificati­ons Bombardier has made to the streetcar design to address problems that have cropped up, which can require retrofitti­ng parts on cars already delivered. For instance, documents obtained by the Star show Bombardier is in the process of replacing the driver’s cab doors on more than 100 of the cars, making alteration­s to auxiliary power supply units on 157 cars, and changing emergency stop buttons on 165 vehicles.

Interviews with TTC sources suggest there is disagreeme­nt about the quality of the streetcars among TTC employees who work with them.

One agency source directly involved in the streetcar program said the maintenanc­e backlog is “spiralling out of control.”

“On a new fleet like this, you don’t expect to see this defect level,” said the source, who asked for anonymity out of fear of reprisal for speaking publicly about internal TTC issues. “It’s not the reliable vehicle we hoped for.”

The source alleged the TTC “is clearly asking us to receive these cars at all costs” and has overlooked defects to help ensure Bombardier delivers cars as quickly as possible.

After years of falling behind schedule on the TTC’s $1-billion order, Bombardier has picked up its production pace and says it’s now on track to meet the deadline of supplying all 204 new cars in the fleet by the end of 2019. The TTC is anxious to take delivery of the new vehicles as its older streetcars, which began service three decades ago, are at the end of their service life.

A separate TTC source with direct knowledge of the repair program said the workload is “manageable” and not indicative of a fundamenta­l problem with the new cars.

The source, who also requested anonymity to speak about internal matters, said it’s normal for the number of work orders to grow as the TTC receives more of the cars, and said only some of the issues are related to defects with the vehicles.

The source said many of the open work orders aren’t related to defects but are preventati­ve maintenanc­e routinely scheduled to ensure vehicles stay in working order.

“We know that there’s issues,” the source said.

“But really the story is here is that (the streetcars are) getting better ... We’re making them more reliable.”

The source acknowledg­ed, however, that the number of cars being removed from service to undergo work is “not ideal,” and “we have more cars being held back out of service for maintenanc­e than what we would like to see.”

Earlier this month the TTC had between 30 and 33 of its new 165 cars out of service for repairs on any given day, according to documents obtained by the Star.

Other documents obtained by the Star show how the TTC accepts delivery of new streetcars from Bombardier that still require work to correct “minor deficienci­es.”

Five of the documents, which are called final acceptance certificat­es and are issued by the TTC as it takes possession of new vehicles, show this summer the TTC took delivery of cars that had problems such as improper gaps between panels on the vehicles’ interior and exterior, faulty paint jobs, and rusted springs on the pantograph device that draws power to the cars from overhead wires.

The vehicle contract the TTC and Bombardier signed in 2009 provides for the transit agency to take delivery of cars with minor deficienci­es if they’re not excessive in number and are corrected quickly.

The contract states that when accepting cars with minor deficienci­es, the TTC “shall retain” a percentage of the streetcar payment price from Bombardier until the deficienci­es are rectified. The amount the TTC is able to withhold works out to about $38,000 per vehicle, according to the transit agency.

In each of the five certificat­es the Star reviewed the TTC didn’t hold back that amount, and made the full payment to Bombardier.

Green said this wasn’t unusual. He described the option to withhold payment as “a mechanism to ensure vehicles are substantia­lly complete and service ready,” and said the TTC hasn’t had to exercise it because “safety and reliabilit­y issues are always dealt with” before final acceptance of each car.

He denied the TTC’s desire to get streetcars delivered quickly has led it to overlook faults or fail to exercise options in the contract to hold Bombardier to account.

“We continue to hold Bombardier accountabl­e when it comes to the timely delivery and quality of these vehicles. But we’ll also work with them to get new vehicles into service as quickly as possible while ensuring they are safe and reliable,” he said.

The streetcars continue to fall short of the reliabilit­y target spelled out in the contract, which states they should travel 35,000 kilometres before experienci­ng a problem that delays service for five minutes or more.

The cars were supposed the reach the target by early last year, but never have. According to the most recent statistics provided by the TTC, in June the cars went a mean distance of about 19,400 km without a significan­t problem. That was down from about 28,000 km in May, but a significan­t improvemen­t from January, when they went only 7,600 km.

TTC reports indicate repeating issues affecting car reliabilit­y include malfunctio­ning doors, HVAC systems, brakes and communicat­ion systems.

Although the cars haven’t yet met the target, Green said the overall trend shows they’re becoming more reliable, and pointed out they perform much better than the TTC’s older streetcars.

Delarosbil, the Bombardier spokespers­on, said the company is “on track to meet our target of 35,000 km between failures by the end of the year.”

A TTC spokespers­on denied the desire to get streetcars delivered quickly has led the agency to overlook faults

 ?? ANDREW FRANCIS WALLACE TORONTO STAR FILE PHOTO ?? Earlier this month the TTC had between 30 and 33 of its 165 new streetcars out of service for repairs on any given day, according to documents obtained by the Star.
ANDREW FRANCIS WALLACE TORONTO STAR FILE PHOTO Earlier this month the TTC had between 30 and 33 of its 165 new streetcars out of service for repairs on any given day, according to documents obtained by the Star.